Elements (Europe) Limited v FK Building Limited

Elements (Europe) Limited v FK Building Limited

The payment application was validly received because, under the contract and established legal principles, '4 days' means any time on the fourth day prior to the Interim Valuation Date, and the law does not count fractions of a day. The contract did not require receipt within site hours or specify 'clear days', so actual receipt by email at 22:07 on 21 October 2022 was effective and valid.

Parties
Claimant (ht 2023 000043) / Defendant (ht 2023 000022): Elements (Europe) Limited; Defendant (ht 2023 000043) / Claimant (ht 2023 000022): FK Building Limited
Jurisdiction
England and Wales
Judgment Date
30 March 2023
Procedural Posture
Commercial Construction Dispute (adjudication Enforcement and Part 8 Claim) / Judgment on Summary Judgment Application and Related Part 8 Claim
Outcome
Part 8 claim dismissed; adjudicator's award enforceable; no summary judgment entered due to settlement.
Legal Topics
Adjudication Enforcement, Summary Judgment, Interpretation of Contract Terms, Payment Application Validity, Time Computation in Contracts

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 13 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Elements (Europe) Limited

Claimant (ht 2023 000043) / Defendant (ht 2023 000022)

FK Building Limited

Defendant (ht 2023 000043) / Claimant (ht 2023 000022)

Procedural Posture

Commercial Construction Dispute (adjudication Enforcement and Part 8 Claim) / Judgment on Summary Judgment Application and Related Part 8 Claim

  1. 1 Whether a payment application served by email at 22:07 on 21 October 2022 was validly 'received not later than 4 days prior to the Interim Valuation Date' under the JCT Sub-Contract
  2. 2 Whether '4 days' in the contract means '4 clear days' or includes the fourth day
  3. 3 Whether the time of day (site hours vs. calendar day) affects validity of receipt under the contract

Ratio Decidendi

The payment application was validly received because, under the contract and established legal principles, '4 days' means any time on the fourth day prior to the Interim Valuation Date, and the law does not count fractions of a day. The contract did not require receipt within site hours or specify 'clear days', so actual receipt by email at 22:07 on 21 October 2022 was effective and valid.

Court Disposition

Part 8 claim dismissed; adjudicator's award enforceable; no summary judgment entered due to settlement.

Orders

  • Part 8 claim dismissed
  • Award enforceable (but not enforced by judgment due to settlement)