Elements (Europe) Limited v FK Building Limited
The payment application was validly received because, under the contract and established legal principles, '4 days' means any time on the fourth day prior to the Interim Valuation Date, and the law does not count fractions of a day. The contract did not require receipt within site hours or specify 'clear days', so actual receipt by email at 22:07 on 21 October 2022 was effective and valid.
- Parties
- Claimant (ht 2023 000043) / Defendant (ht 2023 000022): Elements (Europe) Limited; Defendant (ht 2023 000043) / Claimant (ht 2023 000022): FK Building Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 30 March 2023
- Procedural Posture
- Commercial Construction Dispute (adjudication Enforcement and Part 8 Claim) / Judgment on Summary Judgment Application and Related Part 8 Claim
- Outcome
- Part 8 claim dismissed; adjudicator's award enforceable; no summary judgment entered due to settlement.
- Legal Topics
- Adjudication Enforcement, Summary Judgment, Interpretation of Contract Terms, Payment Application Validity, Time Computation in Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Elements (Europe) Limited
Claimant (ht 2023 000043) / Defendant (ht 2023 000022)
FK Building Limited
Defendant (ht 2023 000043) / Claimant (ht 2023 000022)
Procedural Posture
Commercial Construction Dispute (adjudication Enforcement and Part 8 Claim) / Judgment on Summary Judgment Application and Related Part 8 Claim
Legal Issues
- 1 Whether a payment application served by email at 22:07 on 21 October 2022 was validly 'received not later than 4 days prior to the Interim Valuation Date' under the JCT Sub-Contract
- 2 Whether '4 days' in the contract means '4 clear days' or includes the fourth day
- 3 Whether the time of day (site hours vs. calendar day) affects validity of receipt under the contract
Ratio Decidendi
The payment application was validly received because, under the contract and established legal principles, '4 days' means any time on the fourth day prior to the Interim Valuation Date, and the law does not count fractions of a day. The contract did not require receipt within site hours or specify 'clear days', so actual receipt by email at 22:07 on 21 October 2022 was effective and valid.
Court Disposition
Part 8 claim dismissed; adjudicator's award enforceable; no summary judgment entered due to settlement.
Orders
- Part 8 claim dismissed
- Award enforceable (but not enforced by judgment due to settlement)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment