Battersea Project Phase 2 Development Company Limited v QFS Scaffolding Limited
The saving provision in clause 1.8.2 was engaged by timely commencement of adjudication proceedings challenging the Final Payment Notice. The proceedings were not abandoned, as QFS manifested a continuing intention to resolve the dispute, evidenced by ongoing negotiations and subsequent re-commencement of adjudication on the same subject matter. The Final Payment Notice was therefore subject to the adjudicator’s decision, and summary judgment was granted for the sum declared by the adjudicator. The claim for summary judgment in respect of contractual interest was dismissed for lack of evidential basis.
- Parties
- Part 8 Claimant/part 7 Defendant: Battersea Project Phase 2 Development Company Limited; Part 8 Defendant/part 7 Claimant: Q. F. S. Scaffolding Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 19 November 2024
- Procedural Posture
- Combined Part 8 and Part 7 Claims (declaratory Relief and Summary Judgment) / Judgment After Combined Hearing
- Outcome
- Part 8 claim dismissed; summary judgment granted in Part 7 claim for adjudicator’s declared sum; claim for contractual interest dismissed; parties to be heard on discretionary interest and consequential matters.
- Legal Topics
- Adjudication Enforcement, Conclusive Evidence Clauses, Final Payment Notice, Abandonment of Proceedings, Contractual Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Battersea Project Phase 2 Development Company Limited
Part 8 Claimant/part 7 Defendant
Q. F. S. Scaffolding Limited
Part 8 Defendant/part 7 Claimant
Procedural Posture
Combined Part 8 and Part 7 Claims (declaratory Relief and Summary Judgment) / Judgment After Combined Hearing
Legal Issues
- 1 Whether the Final Payment Notice was conclusive under clause 1.8.1 of the Sub-Contract
- 2 Whether the saving provision in clause 1.8.2 was engaged and its effect
- 3 Whether QFS abandoned the adjudication proceedings
Ratio Decidendi
The saving provision in clause 1.8.2 was engaged by timely commencement of adjudication proceedings challenging the Final Payment Notice. The proceedings were not abandoned, as QFS manifested a continuing intention to resolve the dispute, evidenced by ongoing negotiations and subsequent re-commencement of adjudication on the same subject matter. The Final Payment Notice was therefore subject to the adjudicator’s decision, and summary judgment was granted for the sum declared by the adjudicator. The claim for summary judgment in respect of contractual interest was dismissed for lack of evidential basis.
Court Disposition
Part 8 claim dismissed; summary judgment granted in Part 7 claim for adjudicator’s declared sum; claim for contractual interest dismissed; parties to be heard on discretionary interest and consequential matters.
Orders
- Declaration sought in Part 8 claim refused.
- Summary judgment for QFS in the sum of £3,177,462.85 plus VAT.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment