Lendlease Construction (Europe) Limited v AECOM Limited & Anor.
Permission is granted for the yellow and blue amendments (with costs in the case for yellow, and usual costs order for blue). Permission is refused for the orange amendments (contribution claim) due to insufficient particularisation, lateness, and expiry of limitation. Discontinuance against the Second Defendant and withdrawal of two defects (green and pink amendments) attract costs orders against the Claimant. The Claimant must clarify its pleading regarding reliance on the Project Co judgment.
- Parties
- Claimant: Lendlease Construction (Europe) Limited; First Defendant: AECOM Limited; Second Defendant: AECOM Holdings Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 01 November 2022
- Procedural Posture
- Civil (construction Dispute) / Ruling on Application to Amend Particulars of Claim
- Outcome
- Application to amend allowed in part and refused in part; costs orders made as specified.
- Legal Topics
- Amendment of Pleadings, Costs of Amendments, Discontinuance, Contribution Claims, Limitation Periods
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Lendlease Construction (Europe) Limited
Claimant
AECOM Limited
First Defendant
AECOM Holdings Ltd
Second Defendant
Procedural Posture
Civil (construction Dispute) / Ruling on Application to Amend Particulars of Claim
Legal Issues
- 1 Whether to grant permission for various categories of amendments to the Particulars of Claim
- 2 Appropriate costs orders for each category of amendment
- 3 Whether discontinuance against the Second Defendant and certain claims requires costs orders under CPR 38
Ratio Decidendi
Permission is granted for the yellow and blue amendments (with costs in the case for yellow, and usual costs order for blue). Permission is refused for the orange amendments (contribution claim) due to insufficient particularisation, lateness, and expiry of limitation. Discontinuance against the Second Defendant and withdrawal of two defects (green and pink amendments) attract costs orders against the Claimant. The Claimant must clarify its pleading regarding reliance on the Project Co judgment.
Court Disposition
Application to amend allowed in part and refused in part; costs orders made as specified.
Orders
- Permission granted for yellow amendments; costs in the case.
- Permission granted for blue amendments; Claimant to pay Defendants' costs of and occasioned by the amendments; Defendants permitted to serve further factual evidence by 8 November.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment