Energy Works (Hull) Ltd v MW High Tech Projects UK Ltd & Ors [2020] EWHC 2537 (TCC) (24 September 2020)
On termination for contractor default, MW assigned all accrued and future rights under the Sub-Contract to EWHL; assignment did not transfer obligations and did not amount to novation. MW cannot pursue direct claims against Outotec under the Sub-Contract for accrued rights. MW and Outotec are not liable for 'same damage' under the Civil Liability (Contribution) Act 1978 in respect of delay damages, termination losses, or defects; MW's contribution claim fails.
- Citation
- [2020] EWHC 2537 (TCC)
- Parties
- Claimant: Energy Works (Hull) Limited; First Defendant / Part 20 Claimant: MW High Tech Projects UK Limited; Second Defendant: M&W Group GmbH; First Defendant / Part 20 Defendant: Outotec (USA) Inc
- Jurisdiction
- England and Wales
- Judgment Date
- 24 September 2020
- Procedural Posture
- Commercial Construction Dispute / Preliminary Issues Determination
- Outcome
- Preliminary issues determined against MW; assignment transferred all rights to EWHL, no novation, no contribution claim.
- Legal Topics
- Assignment of Contract, Novation, Contribution Claims, Termination for Default, Liquidated Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Energy Works (Hull) Limited
Claimant
MW High Tech Projects UK Limited
First Defendant / Part 20 Claimant
M&W Group GmbH
Second Defendant
Outotec (USA) Inc
First Defendant / Part 20 Defendant
Procedural Posture
Commercial Construction Dispute / Preliminary Issues Determination
Legal Issues
- 1 Effect of assignment of subcontract: whether accrued and future rights transferred
- 2 Whether assignment also transferred obligations (novation)
- 3 Whether MW can pursue contribution claims against Outotec for 'same damage' under Civil Liability (Contribution) Act 1978
Ratio Decidendi
On termination for contractor default, MW assigned all accrued and future rights under the Sub-Contract to EWHL; assignment did not transfer obligations and did not amount to novation. MW cannot pursue direct claims against Outotec under the Sub-Contract for accrued rights. MW and Outotec are not liable for 'same damage' under the Civil Liability (Contribution) Act 1978 in respect of delay damages, termination losses, or defects; MW's contribution claim fails.
Court Disposition
Preliminary issues determined against MW; assignment transferred all rights to EWHL, no novation, no contribution claim.
Orders
- MW cannot pursue claims against Outotec under the Sub-Contract for accrued rights.
- MW's contribution claim under the Civil Liability (Contribution) Act 1978 is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment