Sysmex (UK) Ltd v Imperial College Healthcare NHS Trust [2017] EWHC 1824 (TCC) (21 July 2017)
Damages would be an adequate remedy for Sysmex if the suspension is lifted and they succeed at trial, but damages would not be an adequate remedy for the Trust if the suspension is continued and they succeed at trial, due to the risk to patient care and significant cost savings. The balance of convenience overwhelmingly favours lifting the suspension.
- Citation
- [2017] EWHC 1824 (TCC)
- Parties
- Claimant/respondent: Sysmex (UK) Limited; Defendant/applicant: Imperial College Healthcare NHS Trust
- Jurisdiction
- England and Wales
- Judgment Date
- 21 July 2017
- Procedural Posture
- Interim Application in Procurement Proceedings / Application to Lift Automatic Suspension Under Regulation 96(1)(a) of the Public Contracts Regulations 2015
- Outcome
- Application granted; automatic suspension lifted.
- Legal Topics
- Automatic Suspension, Adequacy of Damages, Balance of Convenience, Interim Injunctions, Public Contracts Regulations 2015
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sysmex (UK) Limited
Claimant/respondent
Imperial College Healthcare NHS Trust
Defendant/applicant
Procedural Posture
Interim Application in Procurement Proceedings / Application to Lift Automatic Suspension Under Regulation 96(1)(a) of the Public Contracts Regulations 2015
Legal Issues
- 1 Whether the automatic suspension on contract award should be lifted under Regulation 96(1)(a) of the Public Contracts Regulations 2015
- 2 Whether there is a serious issue to be tried
- 3 Whether damages are an adequate remedy for the claimant and/or defendant
Ratio Decidendi
Damages would be an adequate remedy for Sysmex if the suspension is lifted and they succeed at trial, but damages would not be an adequate remedy for the Trust if the suspension is continued and they succeed at trial, due to the risk to patient care and significant cost savings. The balance of convenience overwhelmingly favours lifting the suspension.
Court Disposition
Application granted; automatic suspension lifted.
Orders
- The automatic suspension on the award of the managed services contract to Abbott Laboratories Limited is lifted.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment