Martell v Roszkowski & Ors [2024] EWHC 840 (TCC) (16 April 2024)
GSB breached the building contract by failing to use RC35 concrete and failing to comply with the Structural Specification after 15 April 2015. The concrete did not meet the required specification, causing the need for remedial works. MGA breached its duty by failing to monitor compliance with specification, failing to require testing, and failing to notify the claimant of breaches. Both breaches caused the claimant's loss. The claimant did not commit a repudiatory breach; GSB is not entitled to lost profit damages. The claimant's losses are recoverable subject to assessment.
- Citation
- [2024] EWHC 840 (TCC)
- Parties
- Claimant: Miss Perdita Martell; First Defendant: Mr Grzegorz Roszkowski; Second Defendant: Mr Slawomir Walczak; Third Defendant: Martin Gustyn & Associates Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 16 April 2024
- Procedural Posture
- Civil Technology and Construction / Final Judgment After Trial
- Outcome
- Claim allowed against GSB and MGA; counterclaim dismissed.
- Legal Topics
- Breach of Contract, Defective Works, Duty of Care, Remedial Costs, Mitigation of Loss, Repudiatory Breach, Professional Duties
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Miss Perdita Martell
Claimant
Mr Grzegorz Roszkowski
First Defendant
Mr Slawomir Walczak
Second Defendant
Martin Gustyn & Associates Ltd
Third Defendant
Procedural Posture
Civil Technology and Construction / Final Judgment After Trial
Legal Issues
- 1 Did GSB breach the building contract by failing to use concrete of the correct specification and failing to design/install a suitable waterproofing system?
- 2 Did MGA breach its contractual duty by failing to monitor works and ensure compliance with specification, and by failing to advise on waterproofing?
- 3 Did the breaches cause the claimant's loss?
Ratio Decidendi
GSB breached the building contract by failing to use RC35 concrete and failing to comply with the Structural Specification after 15 April 2015. The concrete did not meet the required specification, causing the need for remedial works. MGA breached its duty by failing to monitor compliance with specification, failing to require testing, and failing to notify the claimant of breaches. Both breaches caused the claimant's loss. The claimant did not commit a repudiatory breach; GSB is not entitled to lost profit damages. The claimant's losses are recoverable subject to assessment.
Court Disposition
Claim allowed against GSB and MGA; counterclaim dismissed.
Orders
- GSB and MGA liable for remedial costs; quantum to be assessed.
- GSB's counterclaim for lost profit dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment