Vyas & Anor v Goraya, (t/a Taj Construction Roofing)
The appeal was allowed only to the extent of increasing the damages by £341.20 for evidenced propane gas and equipment hire costs. The trial judge's approach to quantum, including adopting the median expert figure for remedial works and dismissing other heads of claim, was correct. The appellants failed to prove entitlement to further sums, and the judge's findings on distress and inconvenience were reasonable and supported by the evidence. The liquidated damages clause was not proved to be incorporated. No further award was justified.
- Parties
- Claimant/appellant: Prakash Vyas; Claimant/appellant: Minaxi Vyas; Defendant/respondent: Raj Goraya, T/A Taj Construction Roofing
- Jurisdiction
- England and Wales
- Judgment Date
- 09 November 2016
- Procedural Posture
- Civil Appeal / Appeal Judgment
- Outcome
- Appeal allowed in part; damages increased by £341.20; all other grounds dismissed.
- Legal Topics
- Breach of Contract, Damages, Building Contracts, Quantum of Damages, Liquidated Damages, Distress and Inconvenience
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Prakash Vyas
Claimant/appellant
Minaxi Vyas
Claimant/appellant
Raj Goraya, T/A Taj Construction Roofing
Defendant/respondent
Procedural Posture
Civil Appeal / Appeal Judgment
Legal Issues
- 1 Whether the trial judge erred in the quantum of damages awarded for breach of a building contract
- 2 Whether additional heads of claim should have been allowed
- 3 Whether the judge properly applied the law on damages for distress and inconvenience
Ratio Decidendi
The appeal was allowed only to the extent of increasing the damages by £341.20 for evidenced propane gas and equipment hire costs. The trial judge's approach to quantum, including adopting the median expert figure for remedial works and dismissing other heads of claim, was correct. The appellants failed to prove entitlement to further sums, and the judge's findings on distress and inconvenience were reasonable and supported by the evidence. The liquidated damages clause was not proved to be incorporated. No further award was justified.
Court Disposition
Appeal allowed in part; damages increased by £341.20; all other grounds dismissed.
Orders
- Damages award varied to £121,000.64 in place of £120,659.44
- Directions for written submissions on costs of the appeal
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment