Conocophillips Petroleum Company UK Ltd v v Snamprogetti Ltd & Anor
Snamprogetti was in breach of contract in certain respects, including design errors relating to the HIPS, blowdown sequence, and other minor items. However, the principal claim for damages relating to vibration and the abandonment of the fuel gas compressor failed, as Snamprogetti met the required standard of care and the abandonment was not caused by its breach. Damages for consequential loss and mitigation (including Seafox costs) were contractually excluded. Only limited damages for specific proven breaches were awarded. Snamprogetti succeeded on its counterclaim for unpaid sums and a proportion of additional design hours, resulting in a net judgment in its favour.
- Parties
- Claimant: ConocoPhillips Petroleum Company UK Limited (formerly Phillips Petroleum Company United Kingdom Limited); First Defendant: Snamprogetti Limited; Second Defendant: Snamprogetti International S.A.
- Jurisdiction
- England and Wales
- Judgment Date
- 02 October 2003
- Procedural Posture
- Civil (commercial/construction) / Judgment After Full Trial
- Outcome
- Claim for substantial damages dismissed; limited damages awarded for minor breaches; counterclaim by Snamprogetti allowed; net judgment for Snamprogetti.
- Legal Topics
- Breach of Contract, Damages, Professional Negligence, Standard of Care, Consequential Loss, Remedial Works, Design Defects
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
ConocoPhillips Petroleum Company UK Limited (formerly Phillips Petroleum Company United Kingdom Limited)
Claimant
Snamprogetti Limited
First Defendant
Snamprogetti International S.A.
Second Defendant
Procedural Posture
Civil (commercial/construction) / Judgment After Full Trial
Legal Issues
- 1 What was the contractual standard of care required of Snamprogetti?
- 2 Was Snamprogetti in breach of contract in its design and engineering services?
- 3 Are damages for consequential loss, including loss of revenue and mitigation costs, recoverable under the contract?
Ratio Decidendi
Snamprogetti was in breach of contract in certain respects, including design errors relating to the HIPS, blowdown sequence, and other minor items. However, the principal claim for damages relating to vibration and the abandonment of the fuel gas compressor failed, as Snamprogetti met the required standard of care and the abandonment was not caused by its breach. Damages for consequential loss and mitigation (including Seafox costs) were contractually excluded. Only limited damages for specific proven breaches were awarded. Snamprogetti succeeded on its counterclaim for unpaid sums and a proportion of additional design hours, resulting in a net judgment in its favour.
Court Disposition
Claim for substantial damages dismissed; limited damages awarded for minor breaches; counterclaim by Snamprogetti allowed; net judgment for Snamprogetti.
Orders
- Claimant awarded £70,510 (72.66% of £97,052) for minor breaches.
- Counterclaimant (Snamprogetti) awarded £250,455 for unpaid sums and additional design hours.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment