MALLINO DEVELOPMENT LIMITED v ESSEX DEMOLITION CONTRACTORS LIMITED
Mallino breached clause 2 of the Variation Contract by failing to re-tender Section 3 Works including EDC. The minimum contractual obligation principle does not apply because the contract imposed a mandatory obligation to re-tender. EDC had a real and substantial chance of being awarded Section 3 Works, and damages should be assessed based on the likelihood of contract award, not the minimum obligation. EDC is entitled to damages reflecting a 66% chance of success, calculated on the proven quantum of lost profit and overhead contribution.
- Parties
- Appellant/claimant: Mallino Development Limited; Respondent/defendant: Essex Demolition Contractors Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 10 June 2022
- Procedural Posture
- Civil / Final Judgment After Trial
- Outcome
- EDC’s counterclaim succeeds in part; damages awarded.
- Legal Topics
- Breach of Contract, Damages, Loss of Chance, Tender Process, Variation Contract, Overhead and Profit Contribution
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Mallino Development Limited
Appellant/claimant
Essex Demolition Contractors Limited
Respondent/defendant
Procedural Posture
Civil / Final Judgment After Trial
Legal Issues
- 1 Is EDC entitled to recover profit/fixed overhead contribution for works it may have secured as a result of a successful tender for section 3 of the Works?
- 2 What are the principles by which EDC’s entitlement to recover lost profits and/or loss of overheads contribution in respect of the Section 3 Works are to be measured?
- 3 Is the correct measure of loss to assess the minimum contractual obligation available to Mallino?
Ratio Decidendi
Mallino breached clause 2 of the Variation Contract by failing to re-tender Section 3 Works including EDC. The minimum contractual obligation principle does not apply because the contract imposed a mandatory obligation to re-tender. EDC had a real and substantial chance of being awarded Section 3 Works, and damages should be assessed based on the likelihood of contract award, not the minimum obligation. EDC is entitled to damages reflecting a 66% chance of success, calculated on the proven quantum of lost profit and overhead contribution.
Court Disposition
EDC’s counterclaim succeeds in part; damages awarded.
Orders
- EDC awarded damages assessed at 66% of £321,391.71, being £212,118.53.
- Further hearing to be fixed on interest, costs, and treatment of sums paid pursuant to Second Adjudication Decision.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment