McGlinn v Waltham Contractors Ltd [2007] EWHC 149 (TCC) (21 February 2007)
The court held that while there were defects in the design and construction of Maison d'Or attributable to breaches by the defendants, the claimant was not entitled to the cost of demolition and total rebuild, as this was disproportionate and unreasonable. Damages were limited to the reasonable cost of repair of the proven defects. The absence of proper records and the claimant's own conduct were relevant but did not absolve the defendants of liability for their breaches. The court assessed damages on a repair basis, not a rebuild basis.
- Citation
- [2007] EWHC 149 (TCC)
- Parties
- Claimant: Ian McGlinn; First Defendant: Waltham Contractors Ltd; Second Defendant: Huw Thomas Associates; Third Defendant: DJ Hartigan & Associates Ltd; Fourth Defendant: Wilson Large & Partners
- Jurisdiction
- England and Wales
- Judgment Date
- 21 February 2007
- Procedural Posture
- Civil Construction/professional Negligence / High Court Trial Judgment
- Outcome
- Claim partly allowed
- Legal Topics
- Breach of Contract, Negligence by Construction Professionals, Assessment of Damages, Causation, Standard of Care in Design and Construction, Remedies for Defective Works
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Ian McGlinn
Claimant
Waltham Contractors Ltd
First Defendant
Huw Thomas Associates
Second Defendant
DJ Hartigan & Associates Ltd
Third Defendant
Wilson Large & Partners
Fourth Defendant
Procedural Posture
Civil Construction/professional Negligence / High Court Trial Judgment
Legal Issues
- 1 Whether the defendants breached contractual and/or tortious duties in the design, construction, and management of Maison d'Or.
- 2 Whether the claimant was entitled to demolish the property and claim damages for total rebuild or only for repair.
- 3 Assessment of the standard of care and contractual obligations of each defendant.
Ratio Decidendi
The court held that while there were defects in the design and construction of Maison d'Or attributable to breaches by the defendants, the claimant was not entitled to the cost of demolition and total rebuild, as this was disproportionate and unreasonable. Damages were limited to the reasonable cost of repair of the proven defects. The absence of proper records and the claimant's own conduct were relevant but did not absolve the defendants of liability for their breaches. The court assessed damages on a repair basis, not a rebuild basis.
Court Disposition
Claim partly allowed
Orders
- Damages awarded to the claimant limited to the reasonable cost of repair of proven defects, not the cost of demolition and rebuild.
- Specific quantum to be assessed per itemized schedule against each defendant.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment