Zagora Management Ltd & Ors v Zurich Insurance Plc & Ors [2019] EWHC 140 (TCC) (30 January 2019)
Zagora failed against ZIP because there was no legally binding agreement to rectify and Zagora was not an insured under the building warranty. The individual leaseholder claimants succeeded against ZIP/EWIC as the defects fell within policy cover, but recovery was limited to the aggregate purchase prices of their flats due to policy limits. Claims against ZBC failed because, although ZBC acted negligently and made untrue representations, the requisite reliance and intention for deceit were not established.
- Citation
- [2019] EWHC 140 (TCC)
- Parties
- Claimant: Zagora Management Limited & Others; First Defendant: Zurich Insurance plc; Second Defendant: Zurich Building Control Services Limited; Third Defendant: East West Insurance Company Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 30 January 2019
- Procedural Posture
- Civil Technology and Construction Court / Final Judgment After Trial
- Outcome
- Partially allowed
- Legal Topics
- Building Warranties, Professional Negligence, Deceit, Limitation of Liability, Interpretation of Insurance Policies, Building Regulations Compliance, Remedial Works, Damages Quantification
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Zagora Management Limited & Others
Claimant
Zurich Insurance plc
First Defendant
Zurich Building Control Services Limited
Second Defendant
East West Insurance Company Limited
Third Defendant
Procedural Posture
Civil Technology and Construction Court / Final Judgment After Trial
Legal Issues
- 1 Whether Zagora had a binding agreement to rectify with ZIP
- 2 Whether Zagora was an insured under the building warranty
- 3 Whether the individual leaseholder claimants are entitled to recover under the building warranties
Ratio Decidendi
Zagora failed against ZIP because there was no legally binding agreement to rectify and Zagora was not an insured under the building warranty. The individual leaseholder claimants succeeded against ZIP/EWIC as the defects fell within policy cover, but recovery was limited to the aggregate purchase prices of their flats due to policy limits. Claims against ZBC failed because, although ZBC acted negligently and made untrue representations, the requisite reliance and intention for deceit were not established.
Court Disposition
Partially allowed
Orders
- Zagora's claims against ZIP dismissed
- Individual leaseholder claimants' claims against ZIP/EWIC allowed, limited to £3,634,074 (aggregate purchase prices)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment