Bam Glory Mill Ltd v Balicrest Ltd & Anor
The particulars of claim, as supplemented by the response to the request for further information, now sufficiently identify the alleged obstructions and their locations. While the allocation of responsibility between defendants remains unclear, this does not render the claim abusive or fatally defective. The claim is not analogous to Nomura, as the claimant intends to prosecute the action and has set out the basis of the claim in a rudimentary way. The application to strike out is refused, but the claimant must further particularise the allocation of responsibility and loss.
- Parties
- Claimant: BAM Glory Mill Limited; First Defendant: Balicrest Limited; Second Defendant: McGee Civil Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 03 October 2018
- Procedural Posture
- Civil (technology and Construction Court) / Application to Strike Out Particulars of Claim or for Further Information
- Outcome
- Application to strike out refused; further particulars ordered.
- Legal Topics
- Collateral Warranties, Limitation Periods, Particularisation of Claims, Abuse of Process, Remediation Obligations
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
BAM Glory Mill Limited
Claimant
Balicrest Limited
First Defendant
McGee Civil Engineering Limited
Second Defendant
Procedural Posture
Civil (technology and Construction Court) / Application to Strike Out Particulars of Claim or for Further Information
Legal Issues
- 1 Whether the particulars of claim should be struck out for lack of particularity or as an abuse of process
- 2 Whether the claims are sufficiently particularised as to the nature, location, and responsibility for alleged obstructions
- 3 Whether the claim falls within the Nomura abuse of process principle
Ratio Decidendi
The particulars of claim, as supplemented by the response to the request for further information, now sufficiently identify the alleged obstructions and their locations. While the allocation of responsibility between defendants remains unclear, this does not render the claim abusive or fatally defective. The claim is not analogous to Nomura, as the claimant intends to prosecute the action and has set out the basis of the claim in a rudimentary way. The application to strike out is refused, but the claimant must further particularise the allocation of responsibility and loss.
Court Disposition
Application to strike out refused; further particulars ordered.
Orders
- Claimant to state for each defendant and each obstruction whether breach of contract is alleged and the supporting facts.
- Claimant to provide full details of loss and damage claimed for each defendant.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment