Dutton & Anor v Blaby District Council [2005] EWLands ACQ_132_2004 (17 May 2005)
Schedule 3 rights to rebuild a building existing as of July 1948 are not extinguished by abandonment of residential use; compensation must assume planning permission to rebuild, but the value is significantly affected by the lack of vehicular access and services, reducing the market value to £5,000.
- Citation
- [2005] EWLands ACQ_132_2004
- Parties
- Claimant: Eric Roland Dutton; Claimant: David William Black; Acquiring Authority: Blaby District Council
- Jurisdiction
- England and Wales
- Judgment Date
- 17 May 2005
- Procedural Posture
- Compensation Reference Under Lands Tribunal Act 1949 / Interim Decision on Compensation Assessment
- Outcome
- Interim decision; further submissions invited on access and valuation issues.
- Legal Topics
- Compensation for Compulsory Acquisition, Abandonment of Use, Schedule 3 Rights Under Town and Country Planning Act 1990, Valuation of Derelict Land, Assumptions of Planning Permission
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Eric Roland Dutton
Claimant
David William Black
Claimant
Blaby District Council
Acquiring Authority
Procedural Posture
Compensation Reference Under Lands Tribunal Act 1949 / Interim Decision on Compensation Assessment
Legal Issues
- 1 Whether Schedule 3 rights to rebuild under Town and Country Planning Act 1990 survive abandonment of residential use
- 2 Effect of lack of vehicular access and services on compensation value
Ratio Decidendi
Schedule 3 rights to rebuild a building existing as of July 1948 are not extinguished by abandonment of residential use; compensation must assume planning permission to rebuild, but the value is significantly affected by the lack of vehicular access and services, reducing the market value to £5,000.
Court Disposition
Interim decision; further submissions invited on access and valuation issues.
Orders
- Each party to lodge further evidence and argument within 14 days on whether other land is required for access/services and the valuation impact.
- Final determination of compensation deferred pending further submissions.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment