Weston Homes PLC v Henley Developments 211 Limited & Anor

Weston Homes PLC v Henley Developments 211 Limited & Anor

The contract's language in clauses 23.2 and 23.2.1 is clear and unqualified, allowing either party to terminate and recover the deposit if the Compliance Date has not occurred by the Relevant Date, regardless of the cause. The presumption that a party cannot rely on its own breach is displaced by the express terms and the scheme of the contract. There is no basis for implying a term to the contrary.

Parties
Claimant: Weston Homes PLC; First Defendant: Henley Developments 211 Limited; Second Defendant: Henley Property Investments (UK) LLP
Jurisdiction
England and Wales
Judgment Date
19 December 2024
Procedural Posture
Civil (commercial/property) / Summary Judgment Application
Outcome
Summary judgment for the claimant
Legal Topics
Construction of Contract, Implied Terms, Termination of Contract, Return of Deposit, Breach of Contract

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 11 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Weston Homes PLC

Claimant

Henley Developments 211 Limited

First Defendant

Henley Property Investments (UK) LLP

Second Defendant

Procedural Posture

Civil (commercial/property) / Summary Judgment Application

  1. 1 Whether the claimant is entitled to summary judgment for the return of its deposit under clause 23.2.1 of the contract
  2. 2 Whether the right to terminate under clause 23.2.1 is precluded if the relevant circumstances arise due to the claimant's own breach
  3. 3 Whether a term should be implied into the contract to prevent a party relying on its own breach to terminate and recover the deposit

Ratio Decidendi

The contract's language in clauses 23.2 and 23.2.1 is clear and unqualified, allowing either party to terminate and recover the deposit if the Compliance Date has not occurred by the Relevant Date, regardless of the cause. The presumption that a party cannot rely on its own breach is displaced by the express terms and the scheme of the contract. There is no basis for implying a term to the contrary.

Court Disposition

Summary judgment for the claimant

Orders

  • Return of the deposit to Weston Homes PLC