Sembawang Corporation Ltd. v Pacific Ocean Shipping Corp & Anor [2000] EWHC 225 (Comm) (11 July 2000)
The assessment under Article 37.1(e) must be made by reference to the contractual delivery date as extended by any disputed variation orders already issued at the time of assessment, and not by reference to possible future or anticipated variation orders. The Tribunal's restrictive construction is correct in law, provides commercial certainty, and is consistent with the contract as a whole.
- Citation
- [2000] EWHC 225 (Comm)
- Parties
- Claimant/respondent in the Arbitration: Sembawang Corporation Limited; Defendants/claimants in the Arbitration: Pacific Ocean Shipping Corporation Societe d'Exploitation du Solitaire SA
- Jurisdiction
- England and Wales
- Judgment Date
- 11 July 2000
- Procedural Posture
- Arbitration Appeal / Judgment on Appeal From Arbitral Award
- Outcome
- Appeal dismissed
- Legal Topics
- Construction of Contract Terms, Arbitration Procedure, Shipbuilding Contracts, Variation Orders, Termination Rights
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Sembawang Corporation Limited
Claimant/respondent in the Arbitration
Pacific Ocean Shipping Corporation Societe d'Exploitation du Solitaire SA
Defendants/claimants in the Arbitration
Procedural Posture
Arbitration Appeal / Judgment on Appeal From Arbitral Award
Legal Issues
- 1 Proper construction of Article 37.1(e) of the contract regarding termination rights
- 2 Whether future or anticipated variation orders can extend the contractual delivery date for assessment under Article 37.1(e)
- 3 Effect of information provided by Owners about probable delivery dates of equipment
Ratio Decidendi
The assessment under Article 37.1(e) must be made by reference to the contractual delivery date as extended by any disputed variation orders already issued at the time of assessment, and not by reference to possible future or anticipated variation orders. The Tribunal's restrictive construction is correct in law, provides commercial certainty, and is consistent with the contract as a whole.
Court Disposition
Appeal dismissed
Orders
- The appeal is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment