Munin Navigation Company Ltd & Anor v Petrodel Resources Ltd ('Munin Explorer')

Munin Navigation Company Ltd & Anor v Petrodel Resources Ltd ('Munin Explorer')

Exhibit A6 did not constitute a binding contractual obligation to survey only the lines listed; the contract allowed for post-contract designation of survey lines by the Company. Munin performed the work as designated post-novation and is entitled to payment. The defence and counterclaim had no real prospect of success, justifying summary judgment.

Parties
Claimant/respondent: Munin Navigation Company Ltd; Defendant/appellant: Petrodel Resources Ltd
Jurisdiction
England and Wales
Judgment Date
21 February 2012
Procedural Posture
Civil Appeal / Appeal From Summary Judgment
Outcome
Appeal dismissed; summary judgment for Munin affirmed.
Legal Topics
Construction of Contract Terms, Novation, Summary Judgment, Obligations Under Service Contracts

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Munin Navigation Company Ltd

Claimant/respondent

Petrodel Resources Ltd

Defendant/appellant

Procedural Posture

Civil Appeal / Appeal From Summary Judgment

  1. 1 Whether Exhibit A6 lines were contractually binding as survey obligations
  2. 2 Whether post-novation designations by the Company determined survey obligations
  3. 3 Whether summary judgment was appropriate given the facts

Ratio Decidendi

Exhibit A6 did not constitute a binding contractual obligation to survey only the lines listed; the contract allowed for post-contract designation of survey lines by the Company. Munin performed the work as designated post-novation and is entitled to payment. The defence and counterclaim had no real prospect of success, justifying summary judgment.

Court Disposition

Appeal dismissed; summary judgment for Munin affirmed.

Orders

  • Petrodel to pay Munin the invoiced amounts for survey work performed.
  • Counterclaim by Petrodel dismissed.