Petromec Inc v Petroleo Brasileiro SA Petrobras & Ors [2007] EWHC 1589 (Comm) (06 July 2007)
Petromec must plead and prove its claim by identifying the work done and costs incurred for each change to specification, demonstrating instructions from Petrobras/Brasoil under clause 10 for clause 12.2 claims, and showing reasonableness of work and costs; a global claim methodology is insufficient and does not satisfy contractual requirements.
- Citation
- [2007] EWHC 1589 (Comm)
- Parties
- Claimant: Petromec Inc; Defendant / Part 20 Claimant: Petroleo Brasileiro S.A. Petrobras; Defendant / Part 20 Claimant: Braspetro Oil Services Company; Part 20 Defendant: Petro-Deep Inc.; Part 20 Defendant: Maritima Petroleo e Engenharia Ltda
- Jurisdiction
- England and Wales
- Judgment Date
- 06 July 2007
- Procedural Posture
- Commercial Contract Dispute / Preliminary Issues Hearing
- Outcome
- Petromec's global claim methodology rejected; Petromec must plead and prove claims in accordance with contract requirements.
- Legal Topics
- Contract Interpretation, Variation Orders, Global Claims, Compensation for Specification Changes
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Petromec Inc
Claimant
Petroleo Brasileiro S.A. Petrobras
Defendant / Part 20 Claimant
Braspetro Oil Services Company
Defendant / Part 20 Claimant
Petro-Deep Inc.
Part 20 Defendant
Maritima Petroleo e Engenharia Ltda
Part 20 Defendant
Procedural Posture
Commercial Contract Dispute / Preliminary Issues Hearing
Legal Issues
- 1 Proper construction of clauses 12.1, 12.2, and 12.3 of the Supervision Agreement
- 2 Methodology for assessing reasonable extra costs
- 3 Necessity for separate ascertainment under clauses 12.1 and 12.2
Ratio Decidendi
Petromec must plead and prove its claim by identifying the work done and costs incurred for each change to specification, demonstrating instructions from Petrobras/Brasoil under clause 10 for clause 12.2 claims, and showing reasonableness of work and costs; a global claim methodology is insufficient and does not satisfy contractual requirements.
Court Disposition
Petromec's global claim methodology rejected; Petromec must plead and prove claims in accordance with contract requirements.
Orders
- Petromec must particularise claims by identifying work, instructions, and costs for each change under clauses 12.1 and 12.2.
- Petromec must produce evidence of expenditure and reasonableness for each element claimed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment