Geoquip Marine Operations AG v Tower Resources Cameroon SA & Anor
Following waiver of the condition precedent, Tower remained obligated to secure the licence extension and permits. Clause 4.5 applied to delays caused by Tower’s failure to provide security and/or licence extension, entitling Geoquip to standby charges regardless of which cause was dominant, as Tower was responsible for both.
- Parties
- Claimant/appellant: Geoquip Marine Operations AG; Defendant/respondent: Tower Resources Cameroon SA; Defendant/respondent: Tower Resources PLC
- Jurisdiction
- England and Wales
- Judgment Date
- 21 March 2023
- Procedural Posture
- Civil Appeal / Court of Appeal Judgment
- Outcome
- Appeal allowed in part
- Legal Topics
- Contractual Interpretation, Waiver of Condition Precedent, Concurrent Causation, Standby Charges, Remuneration Under Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Geoquip Marine Operations AG
Claimant/appellant
Tower Resources Cameroon SA
Defendant/respondent
Tower Resources PLC
Defendant/respondent
Procedural Posture
Civil Appeal / Court of Appeal Judgment
Legal Issues
- 1 Whether Geoquip can claim standby charges for delays caused by Tower's failure to provide security for the Vessel under clause 4.5
- 2 Whether the judge was correct to hold that Geoquip could not recover standby charges for delay under clause 4.5 due to the contract being conditional on licence extension
- 3 Whether the judge ought to have found that the only operative cause of delay was the absence of a Presidential decree confirming the licence extension
Ratio Decidendi
Following waiver of the condition precedent, Tower remained obligated to secure the licence extension and permits. Clause 4.5 applied to delays caused by Tower’s failure to provide security and/or licence extension, entitling Geoquip to standby charges regardless of which cause was dominant, as Tower was responsible for both.
Court Disposition
Appeal allowed in part
Orders
- Geoquip is entitled to judgment for an additional sum of US$1,619,541.69 in respect of standby charges for delays caused by Tower’s failure to secure a necessary licence extension and to provide security for the Vessel.
- Permission to amend appellant’s notice refused.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment