Epsom College v Pierse Contracting Southern Ltd [2011] EWCA Civ 1449 (13 December 2011)
The first Part 36 offer made by the claimant was a valid offer under Part 36. Although the judge erred in awarding Part 36 consequences based on the second (withdrawn) offer, it was appropriate to award indemnity costs and enhanced interest from the date the pipe was produced and the contractor was in a position to evaluate the claim properly. The claimant's conduct did not justify a reduction to 60% of costs. The costs of the December site inspection application were properly included as costs in the case.
- Citation
- [2011] EWCA Civ 1449
- Parties
- Claimant / Respondent: Epsom College (A Private Company Limited by Guarantee); Defendant / Appellant: Pierse Contracting Southern Limited (In Liquidation, formerly Bisley Construction Limited)
- Jurisdiction
- England and Wales
- Judgment Date
- 13 December 2011
- Procedural Posture
- Appeal (civil) / Court of Appeal Judgment on Costs Following Trial Judgment in Queen's Bench Division
- Outcome
- Appeal dismissed in substance; costs order varied to award indemnity costs and enhanced interest from 1 November 2010 (after production of the pipe) rather than from the expiry of the second Part 36 offer.
- Legal Topics
- Costs, Part 36 Offers, Indemnity Costs, Interest on Judgment, Conduct of Litigation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Epsom College (A Private Company Limited by Guarantee)
Claimant / Respondent
Pierse Contracting Southern Limited (In Liquidation, formerly Bisley Construction Limited)
Defendant / Appellant
Procedural Posture
Appeal (civil) / Court of Appeal Judgment on Costs Following Trial Judgment in Queen's Bench Division
Legal Issues
- 1 Whether the judge erred in awarding indemnity costs and enhanced interest under Part 36 based on the claimant's offers; whether the claimant should have been awarded all its costs or only a percentage due to conduct; whether the Part 36 offers were valid; whether costs of a late site inspection application should be awarded to the contractor.
Ratio Decidendi
The first Part 36 offer made by the claimant was a valid offer under Part 36. Although the judge erred in awarding Part 36 consequences based on the second (withdrawn) offer, it was appropriate to award indemnity costs and enhanced interest from the date the pipe was produced and the contractor was in a position to evaluate the claim properly. The claimant's conduct did not justify a reduction to 60% of costs. The costs of the December site inspection application were properly included as costs in the case.
Court Disposition
Appeal dismissed in substance; costs order varied to award indemnity costs and enhanced interest from 1 November 2010 (after production of the pipe) rather than from the expiry of the second Part 36 offer.
Orders
- Indemnity costs and enhanced interest at 6% on judgment sum and costs awarded to claimant from 1 November 2010.
- Claimant awarded its costs of the whole proceedings, including costs of December 2010 site inspection application.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment