McGlinn v Waltham Contractors Ltd & Ors [2007] EWHC 294 (TCC) (22 February 2007)

McGlinn v Waltham Contractors Ltd & Ors [2007] EWHC 294 (TCC) (22 February 2007)

Wilson Large & Partners are entitled to their costs of and occasioned by the defects issues, as these constitute a distinct part of the proceedings, and their success on these issues is unaffected by the outcome of the later over-valuation trial. The interim payment is assessed at £180,000, reflecting deductions for costs attributable to over-valuation issues and the assessment process.

Citation
[2007] EWHC 294 (TCC)
Parties
Claimant: Ian McGlinn; First Defendant: Waltham Contractors Ltd; Second Defendant: Huw Thomas Associates; Third Defendant: DJ Hartigan & Associates Ltd; Fourth Defendant: Wilson Large & Partners
Jurisdiction
England and Wales
Judgment Date
22 February 2007
Procedural Posture
Civil / Post Trial Costs Determination
Outcome
Costs order in favour of Wilson Large & Partners for defects issues; interim payment ordered.
Legal Topics
Costs Orders, Split Trials, Issue Based Costs, Interim Payments

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 7 Authorities cited 5 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Ian McGlinn

Claimant

Waltham Contractors Ltd

First Defendant

Huw Thomas Associates

Second Defendant

DJ Hartigan & Associates Ltd

Third Defendant

Wilson Large & Partners

Fourth Defendant

Procedural Posture

Civil / Post Trial Costs Determination

  1. 1 Entitlement to costs for defects issues after dismissal of claims against Fourth Defendant
  2. 2 Appropriate timing and form of costs orders in split trials
  3. 3 Assessment of interim payment for costs

Ratio Decidendi

Wilson Large & Partners are entitled to their costs of and occasioned by the defects issues, as these constitute a distinct part of the proceedings, and their success on these issues is unaffected by the outcome of the later over-valuation trial. The interim payment is assessed at £180,000, reflecting deductions for costs attributable to over-valuation issues and the assessment process.

Court Disposition

Costs order in favour of Wilson Large & Partners for defects issues; interim payment ordered.

Orders

  • Wilson Large & Partners awarded costs of defects issues.
  • Interim payment of £180,000 to be paid by 27 March 2007.