McGlinn v Waltham Contractors Ltd & Ors [2007] EWHC 294 (TCC) (22 February 2007)
Wilson Large & Partners are entitled to their costs of and occasioned by the defects issues, as these constitute a distinct part of the proceedings, and their success on these issues is unaffected by the outcome of the later over-valuation trial. The interim payment is assessed at £180,000, reflecting deductions for costs attributable to over-valuation issues and the assessment process.
- Citation
- [2007] EWHC 294 (TCC)
- Parties
- Claimant: Ian McGlinn; First Defendant: Waltham Contractors Ltd; Second Defendant: Huw Thomas Associates; Third Defendant: DJ Hartigan & Associates Ltd; Fourth Defendant: Wilson Large & Partners
- Jurisdiction
- England and Wales
- Judgment Date
- 22 February 2007
- Procedural Posture
- Civil / Post Trial Costs Determination
- Outcome
- Costs order in favour of Wilson Large & Partners for defects issues; interim payment ordered.
- Legal Topics
- Costs Orders, Split Trials, Issue Based Costs, Interim Payments
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Ian McGlinn
Claimant
Waltham Contractors Ltd
First Defendant
Huw Thomas Associates
Second Defendant
DJ Hartigan & Associates Ltd
Third Defendant
Wilson Large & Partners
Fourth Defendant
Procedural Posture
Civil / Post Trial Costs Determination
Legal Issues
- 1 Entitlement to costs for defects issues after dismissal of claims against Fourth Defendant
- 2 Appropriate timing and form of costs orders in split trials
- 3 Assessment of interim payment for costs
Ratio Decidendi
Wilson Large & Partners are entitled to their costs of and occasioned by the defects issues, as these constitute a distinct part of the proceedings, and their success on these issues is unaffected by the outcome of the later over-valuation trial. The interim payment is assessed at £180,000, reflecting deductions for costs attributable to over-valuation issues and the assessment process.
Court Disposition
Costs order in favour of Wilson Large & Partners for defects issues; interim payment ordered.
Orders
- Wilson Large & Partners awarded costs of defects issues.
- Interim payment of £180,000 to be paid by 27 March 2007.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment