Mallino Development Ltd v Essex Demolition Contractors Ltd [2022] EWHC 1418 (TCC) (10 June 2022)

Mallino Development Ltd v Essex Demolition Contractors Ltd [2022] EWHC 1418 (TCC) (10 June 2022)

The court held that Mallino was under a mandatory obligation to re-tender the Section 3 Works and include EDC in the process. The minimum contractual obligation principle did not apply because the contract did not provide for alternative methods of performance but imposed a single obligation with discretion as to...

Source-derived case information.

Citation
[2022] EWHC 1418 (TCC)
Parties
Appellant/claimant: Mallino Development Limited; Respondent/defendant: Essex Demolition Contractors Limited
Jurisdiction
England and Wales
Judgment Date
10 June 2022
Procedural Posture
High Court Technology and Construction Court (tcc) Proceedings / Judgment After Trial
Outcome
EDC's counterclaim for loss of profit and overhead contribution succeeds on a loss of a chance basis. Mallino's arguments based on the minimum contractual obligation principle are rejected.
Legal Topics
Damages for Breach of Contract, Loss of Profit, Loss of a Chance, Tendering Obligations, Minimum Contractual Obligation Principle
Construction Law Contract Law Damages for Breach of Contract Loss of Profit Loss of a Chance Tendering Obligations Minimum Contractual Obligation Principle

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Mallino Development Limited

Appellant/claimant

Essex Demolition Contractors Limited

Respondent/defendant

Procedural Posture

High Court Technology and Construction Court (tcc) Proceedings / Judgment After Trial

  1. 1 Is EDC entitled to recover profit/fixed overhead contribution for works it may have secured as a result of a successful tender for section 3 of the Works?
  2. 2 What is the correct measure of loss for EDC's claim?
  3. 3 Would EDC have been appointed for the Section 3 Works if Mallino had complied with the Variation Contract?

Ratio Decidendi

The court held that Mallino was under a mandatory obligation to re-tender the Section 3 Works and include EDC in the process. The minimum contractual obligation principle did not apply because the contract did not provide for alternative methods of performance but imposed a single obligation with discretion as to how it was performed. EDC had a real and substantial chance of being appointed for the Section 3 Works, and was entitled to damages reflecting the lost opportunity to earn profit and overhead contribution, assessed on a loss of a chance basis.

Court Disposition

EDC's counterclaim for loss of profit and overhead contribution succeeds on a loss of a chance basis. Mallino's arguments based on the minimum contractual obligation principle are rejected.

Orders

  • Mallino to pay EDC damages for loss of profit and overhead contribution assessed at £282,770.97.
  • Interest to be paid to EDC on the awarded sum.