Struthers & Anor v Davies (t/a Alastair Davies Building) & Anor [2022] EWHC 333 (TCC) (18 February 2022)
The First Defendant was in repudiatory breach of contract by failing to progress and complete the works, refusing to purchase materials, and abandoning the project. The Claimants were entitled to accept this repudiation and recover damages for defective and incomplete works, as well as consequential losses, based on reasonable expert advice and expenditure. The contract was not validly terminated under its express terms, but lawful termination occurred at common law due to repudiatory breach.
- Citation
- [2022] EWHC 333 (TCC)
- Parties
- Claimant: Gavin Struthers; Claimant: Stacey Struthers; First Defendant: Alastair Davies (trading as 'Alastair Davies Building'); Second Defendant: Design-Cubed Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 18 February 2022
- Procedural Posture
- Civil Construction Dispute / Trial Judgment
- Outcome
- Judgment for the Claimants
- Legal Topics
- Defective Works, Incomplete Works, Contract Termination, Damages, Repudiatory Breach, Variation of Contract, Mitigation of Loss
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Gavin Struthers
Claimant
Stacey Struthers
Claimant
Alastair Davies (trading as 'Alastair Davies Building')
First Defendant
Design-Cubed Limited
Second Defendant
Procedural Posture
Civil Construction Dispute / Trial Judgment
Legal Issues
- 1 What were the agreed contract documents and terms?
- 2 Were the contract terms varied by agreement or conduct?
- 3 Did the First Defendant carry out defective and/or incomplete works?
Ratio Decidendi
The First Defendant was in repudiatory breach of contract by failing to progress and complete the works, refusing to purchase materials, and abandoning the project. The Claimants were entitled to accept this repudiation and recover damages for defective and incomplete works, as well as consequential losses, based on reasonable expert advice and expenditure. The contract was not validly terminated under its express terms, but lawful termination occurred at common law due to repudiatory breach.
Court Disposition
Judgment for the Claimants
Orders
- First Defendant to pay Claimants £349,913.67 after credits for defective and incomplete works and consequential losses.
- Consequential matters as to interest and costs agreed by consent order.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment