Birse Construction Ltd v Eastern Telegraph Company Ltd
Birse Construction is liable for the cost of remedying only those defects for which it was contractually responsible and which were not remedied, but Eastern Telegraph is not entitled to recover the cost of unremedied defects where it had no genuine intention to carry out the works and suffered no actual loss. The March 1994 agreement replaced the original contract's defect regime for snagging items, and ET's rights to withhold or claim further sums are limited accordingly. Retention monies must be released to Birse save for valid set-offs for actual defects. Only nominal damages are recoverable for unremedied defects where no loss is shown.
- Parties
- Claimant/defendant: Birse Construction Limited; Defendant/claimant: Eastern Telegraph Company Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 05 November 2004
- Procedural Posture
- Civil (construction Dispute) / Judgment After Trial
- Outcome
- Judgment for Birse Construction in part; Eastern Telegraph entitled to limited recovery for remedied defects only; nominal damages for unremedied defects; retention monies to be released to Birse subject to set-off for actual defects.
- Legal Topics
- Defective Works, Remedial Works, Damages, Retention Monies, Final Account Settlement, Measure of Damages, Snagging Lists, Architect's Satisfaction, Practical Completion, Making Good Defects
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Birse Construction Limited
Claimant/defendant
Eastern Telegraph Company Limited
Defendant/claimant
Procedural Posture
Civil (construction Dispute) / Judgment After Trial
Legal Issues
- 1 Whether Birse Construction is liable for the cost of remedying defects in the construction of the college.
- 2 Whether Eastern Telegraph is entitled to withhold retention or claim damages for unremedied defects.
- 3 Interpretation and effect of the March 1994 settlement agreement.
Ratio Decidendi
Birse Construction is liable for the cost of remedying only those defects for which it was contractually responsible and which were not remedied, but Eastern Telegraph is not entitled to recover the cost of unremedied defects where it had no genuine intention to carry out the works and suffered no actual loss. The March 1994 agreement replaced the original contract's defect regime for snagging items, and ET's rights to withhold or claim further sums are limited accordingly. Retention monies must be released to Birse save for valid set-offs for actual defects. Only nominal damages are recoverable for unremedied defects where no loss is shown.
Court Disposition
Judgment for Birse Construction in part; Eastern Telegraph entitled to limited recovery for remedied defects only; nominal damages for unremedied defects; retention monies to be released to Birse subject to set-off for actual defects.
Orders
- Birse Construction entitled to payment of retention monies less valid set-offs for actual defects.
- Eastern Telegraph entitled to recover the cost of remedying certain remedied defects for which Birse is liable.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment