Birse Construction Ltd v Eastern Telegraph Company Ltd [2004] EWHC 2512 (TCC) (05 November 2004)
Birse Construction is liable to remedy or pay for all defects listed in snagging sheets as defined in the March 1994 settlement agreement, regardless of whether they constitute breaches under the original contract. Eastern Telegraph is entitled to set-off or recover the estimated costs of remedying outstanding snagging defects against the unpaid balance under clause 3.1, and if the retained sum is insufficient, to recover the balance as a debt under clause 3.3.
- Citation
- [2004] EWHC 2512 (TCC)
- Parties
- Third Part 20 Claimant and Fifth Part 20 Claimant: Birse Construction Limited; Third Part 20 Defendant and Fourth Part 20 Claimant: Eastern Telegraph Company Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 05 November 2004
- Procedural Posture
- Construction Dispute (defects and Retention) / Final Judgment After Trial
- Outcome
- Liability established for Birse Construction for defects as defined in the settlement agreement; Eastern Telegraph entitled to set-off and recovery as per agreement.
- Legal Topics
- Defective Works, Final Account Settlement, Retention, Remedial Works, Interpretation of Settlement Agreement
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Birse Construction Limited
Third Part 20 Claimant and Fifth Part 20 Claimant
Eastern Telegraph Company Limited
Third Part 20 Defendant and Fourth Part 20 Claimant
Procedural Posture
Construction Dispute (defects and Retention) / Final Judgment After Trial
Legal Issues
- 1 Whether Birse Construction is liable for unremedied and remedied defects under the March 1994 settlement agreement
- 2 Whether Eastern Telegraph is entitled to set-off or recover costs for defects not remedied
- 3 Interpretation of 'snagging defects' and scope of contractor's obligations under the settlement agreement
Ratio Decidendi
Birse Construction is liable to remedy or pay for all defects listed in snagging sheets as defined in the March 1994 settlement agreement, regardless of whether they constitute breaches under the original contract. Eastern Telegraph is entitled to set-off or recover the estimated costs of remedying outstanding snagging defects against the unpaid balance under clause 3.1, and if the retained sum is insufficient, to recover the balance as a debt under clause 3.3.
Court Disposition
Liability established for Birse Construction for defects as defined in the settlement agreement; Eastern Telegraph entitled to set-off and recovery as per agreement.
Orders
- Adjustment of ET's claim to account for settlement with MJP (£11,044.29 for Pozament render, £4,654.61 for Armouralia)
- ET entitled to set-off admitted defect values against £13,725 balance under clause 3.1
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment