Yorkshire Water Services Ltd. v Taylor Woodrow Construction Northern Ltd.

Yorkshire Water Services Ltd. v Taylor Woodrow Construction Northern Ltd.

Yorkshire Water failed to prove the SBR plant was unable to meet contractual performance requirements if properly operated; operational difficulties were due to abnormal influent and operational errors, not design defects. Therefore, Yorkshire Water was not entitled to recover remedial costs or liquidated damages under the contract. Taylor Woodrow/Biwater were entitled to extension of time and payment of outstanding sums as per the contract and agreed quantum.

Parties
Claimant/part 20 Defendant (1): Yorkshire Water Services Limited; Defendant/part 20 Claimant (1 & 2): Taylor Woodrow Construction Northern Limited; Part 20 Defendant (2)/part 20 Claimant (3): Biwater Treatment Limited; Part 20 Defendant (3): Elga Limited
Jurisdiction
England and Wales
Judgment Date
08 July 2004
Procedural Posture
Civil (construction/contract) / Final Judgment After Trial
Outcome
Claim dismissed; counterclaim allowed.
Legal Topics
Design and Build Contracts, Performance Guarantees, Liquidated Damages, Defects Liability, Remedial Works, Extension of Time, Final Account, Sludge Settlement, Selector Capacity

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 5 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Yorkshire Water Services Limited

Claimant/part 20 Defendant (1)

Taylor Woodrow Construction Northern Limited

Defendant/part 20 Claimant (1 & 2)

Biwater Treatment Limited

Part 20 Defendant (2)/part 20 Claimant (3)

Elga Limited

Part 20 Defendant (3)

Procedural Posture

Civil (construction/contract) / Final Judgment After Trial

  1. 1 Whether the SBR plant as designed and constructed complied with contractual performance requirements.
  2. 2 Whether Yorkshire Water was entitled to recover costs of remedial works under the contract.
  3. 3 Whether Taylor Woodrow/Biwater were entitled to extension of time and payment of outstanding sums.

Ratio Decidendi

Yorkshire Water failed to prove the SBR plant was unable to meet contractual performance requirements if properly operated; operational difficulties were due to abnormal influent and operational errors, not design defects. Therefore, Yorkshire Water was not entitled to recover remedial costs or liquidated damages under the contract. Taylor Woodrow/Biwater were entitled to extension of time and payment of outstanding sums as per the contract and agreed quantum.

Court Disposition

Claim dismissed; counterclaim allowed.

Orders

  • Yorkshire Water's claims for financial relief, liquidated damages, and declaratory relief dismissed.
  • Dependent Part 20 claims dismissed.