Associated British Ports v Hydro Soil Services NV & Ors [2006] EWHC 1187 (TCC) (23 June 2006)

Associated British Ports v Hydro Soil Services NV & Ors [2006] EWHC 1187 (TCC) (23 June 2006)

The court held that the strengthening works were not fit for their intended purpose and that HSS was responsible for the defective works and the cost of remedying them. The physical condition of the quay wall did not constitute an unforeseeable physical condition within the meaning of clause 12, as it was part of...

Source-derived case information.

Citation
[2006] EWHC 1187 (TCC)
Parties
Claimant: Associated British Ports; Defendant/part 20 Claimant: Hydro Soil Services N.V.; Defendant/part 20 Claimant: Dredging International (UK) Limited; Part 20 Defendant: Haecon N.V.; Part 20 Defendant: Gerling-Konzern Belgie N.V.; Part 20 Defendant: AGF Belgium Insurance N.V.; Part 20 Defendant: Euromaf S.A.
Jurisdiction
England and Wales
Judgment Date
23 June 2006
Procedural Posture
Technology and Construction Court (tcc) Trial / Judgment After Full Trial
Outcome
Claim allowed in part; counterclaim dismissed
Legal Topics
Fitness for Purpose, Unforeseeable Physical Conditions, Design and Construction Liability, Remedial Works, Indemnity and Contribution
Construction Law Contract Law Fitness for Purpose Unforeseeable Physical Conditions Design and Construction Liability Remedial Works Indemnity and Contribution

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Associated British Ports

Claimant

Hydro Soil Services N.V.

Defendant/part 20 Claimant

Dredging International (UK) Limited

Defendant/part 20 Claimant

Haecon N.V.

Part 20 Defendant

Gerling-Konzern Belgie N.V.

Part 20 Defendant

AGF Belgium Insurance N.V.

Part 20 Defendant

Euromaf S.A.

Part 20 Defendant

Procedural Posture

Technology and Construction Court (tcc) Trial / Judgment After Full Trial

  1. 1 Whether the strengthening works were fit for purpose under the contract
  2. 2 Whether the physical condition of the quay wall constituted an unforeseeable physical condition under clause 12
  3. 3 Responsibility for remedial works and associated costs

Ratio Decidendi

The court held that the strengthening works were not fit for their intended purpose and that HSS was responsible for the defective works and the cost of remedying them. The physical condition of the quay wall did not constitute an unforeseeable physical condition within the meaning of clause 12, as it was part of the works to be strengthened and should have been foreseen by an experienced contractor. HSS was not entitled to extra payment under clause 12. Haecon's liability as a subcontractor was considered in relation to indemnity and contribution claims.

Court Disposition

Claim allowed in part; counterclaim dismissed

Orders

  • Declaration that HSS is responsible for defective works and cost of remedying them
  • Damages awarded to ABP for breach of contract