P C Partitions Ltd v Canary Wharf Contractors Ltd & Anor [2004] EWHC 1766 (TCC) (28 July 2004)
No concluded direct contract was formed between PCP and CWC at the March 2003 meeting; the purchase order was an accounting device, not evidence of a new contractual relationship. The subsequent Tripartite Agreement (Direct Payment Agreement) governed the parties' rights regarding direct payments, expressly limiting PCP's rights against CWC. PCP remained a subcontractor to IES, and any entitlement to payment from CWC was strictly as provided in the Tripartite Agreement. Clauses limiting PCP's rights were not contrary to public policy or unenforceable under the Unfair Contract Terms Act 1977 in this commercial context.
- Citation
- [2004] EWHC 1766 (TCC)
- Parties
- Claimant: PC Partitions Limited; Defendant and Part 20 Claimant: Canary Wharf Contractors Limited; Part 20 Defendant: Infinite Environmental Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 28 July 2004
- Procedural Posture
- Commercial Construction Dispute / Preliminary Issues Trial in the Technology and Construction Court
- Outcome
- Claim for direct contractual entitlement against CWC dismissed; rights governed by Tripartite Agreement only.
- Legal Topics
- Formation of Contract, Direct Payment Agreements, Implied Terms, Unfair Contract Terms, Subcontractor Rights
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
PC Partitions Limited
Claimant
Canary Wharf Contractors Limited
Defendant and Part 20 Claimant
Infinite Environmental Services Limited
Part 20 Defendant
Procedural Posture
Commercial Construction Dispute / Preliminary Issues Trial in the Technology and Construction Court
Legal Issues
- 1 Whether a direct contract (the 'CWC Agreement') was formed between PCP and CWC at the March 2003 meeting
- 2 Whether the subsequent 'Direct Payment Agreement' (Tripartite Agreement) superseded or regulated the parties' rights
- 3 Whether PCP was entitled to payment from CWC for all works undertaken after the meeting
Ratio Decidendi
No concluded direct contract was formed between PCP and CWC at the March 2003 meeting; the purchase order was an accounting device, not evidence of a new contractual relationship. The subsequent Tripartite Agreement (Direct Payment Agreement) governed the parties' rights regarding direct payments, expressly limiting PCP's rights against CWC. PCP remained a subcontractor to IES, and any entitlement to payment from CWC was strictly as provided in the Tripartite Agreement. Clauses limiting PCP's rights were not contrary to public policy or unenforceable under the Unfair Contract Terms Act 1977 in this commercial context.
Court Disposition
Claim for direct contractual entitlement against CWC dismissed; rights governed by Tripartite Agreement only.
Orders
- Preliminary issues determined in favour of CWC; PCP's claim for direct payment outside the Tripartite Agreement fails.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment