P C Partitions Ltd v Canary Wharf Contractors Ltd & Anor [2004] EWHC 1766 (TCC) (28 July 2004)

P C Partitions Ltd v Canary Wharf Contractors Ltd & Anor [2004] EWHC 1766 (TCC) (28 July 2004)

No concluded direct contract was formed between PCP and CWC at the March 2003 meeting; the purchase order was an accounting device, not evidence of a new contractual relationship. The subsequent Tripartite Agreement (Direct Payment Agreement) governed the parties' rights regarding direct payments, expressly limiting PCP's rights against CWC. PCP remained a subcontractor to IES, and any entitlement to payment from CWC was strictly as provided in the Tripartite Agreement. Clauses limiting PCP's rights were not contrary to public policy or unenforceable under the Unfair Contract Terms Act 1977 in this commercial context.

Citation
[2004] EWHC 1766 (TCC)
Parties
Claimant: PC Partitions Limited; Defendant and Part 20 Claimant: Canary Wharf Contractors Limited; Part 20 Defendant: Infinite Environmental Services Limited
Jurisdiction
England and Wales
Judgment Date
28 July 2004
Procedural Posture
Commercial Construction Dispute / Preliminary Issues Trial in the Technology and Construction Court
Outcome
Claim for direct contractual entitlement against CWC dismissed; rights governed by Tripartite Agreement only.
Legal Topics
Formation of Contract, Direct Payment Agreements, Implied Terms, Unfair Contract Terms, Subcontractor Rights

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

PC Partitions Limited

Claimant

Canary Wharf Contractors Limited

Defendant and Part 20 Claimant

Infinite Environmental Services Limited

Part 20 Defendant

Procedural Posture

Commercial Construction Dispute / Preliminary Issues Trial in the Technology and Construction Court

  1. 1 Whether a direct contract (the 'CWC Agreement') was formed between PCP and CWC at the March 2003 meeting
  2. 2 Whether the subsequent 'Direct Payment Agreement' (Tripartite Agreement) superseded or regulated the parties' rights
  3. 3 Whether PCP was entitled to payment from CWC for all works undertaken after the meeting

Ratio Decidendi

No concluded direct contract was formed between PCP and CWC at the March 2003 meeting; the purchase order was an accounting device, not evidence of a new contractual relationship. The subsequent Tripartite Agreement (Direct Payment Agreement) governed the parties' rights regarding direct payments, expressly limiting PCP's rights against CWC. PCP remained a subcontractor to IES, and any entitlement to payment from CWC was strictly as provided in the Tripartite Agreement. Clauses limiting PCP's rights were not contrary to public policy or unenforceable under the Unfair Contract Terms Act 1977 in this commercial context.

Court Disposition

Claim for direct contractual entitlement against CWC dismissed; rights governed by Tripartite Agreement only.

Orders

  • Preliminary issues determined in favour of CWC; PCP's claim for direct payment outside the Tripartite Agreement fails.