Purbrick v Cruz & Anor [2020] EWHC 1465 (QB) (11 June 2020)
There was not sufficient material non-disclosure to justify setting aside the freezing injunction. The only significant omission was the claimant's attempt to claim under the company's insurance policy, but this would not have changed the outcome. There remains a good arguable case that Mr Cruz is personally liable under the contract, based on the contract wording, execution, and conduct of the parties. The risk of dissipation is established by Mr Cruz's ties to Mexico and attempts to dispose of UK assets.
- Citation
- [2020] EWHC 1465 (QB)
- Parties
- Claimant: Robert Purbrick; First Defendant: Mark Cruz; Second Defendant: MM Cruz Developments Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 11 June 2020
- Procedural Posture
- Application for Continuation of Freezing Injunction / Post Ex Parte, Return Date Hearing
- Outcome
- Application to set aside the freezing injunction refused; freezing injunction continued.
- Legal Topics
- Freezing Injunctions, Material Non Disclosure, Identity of Contracting Parties, Risk of Dissipation, Breach of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Robert Purbrick
Claimant
Mark Cruz
First Defendant
MM Cruz Developments Ltd
Second Defendant
Procedural Posture
Application for Continuation of Freezing Injunction / Post Ex Parte, Return Date Hearing
Legal Issues
- 1 Whether there was material non-disclosure justifying discharge of the freezing injunction
- 2 Whether there is a good arguable case that Mr Cruz is personally liable under the contract
- 3 Whether there is a real risk of dissipation of assets justifying continuation of the injunction
Ratio Decidendi
There was not sufficient material non-disclosure to justify setting aside the freezing injunction. The only significant omission was the claimant's attempt to claim under the company's insurance policy, but this would not have changed the outcome. There remains a good arguable case that Mr Cruz is personally liable under the contract, based on the contract wording, execution, and conduct of the parties. The risk of dissipation is established by Mr Cruz's ties to Mexico and attempts to dispose of UK assets.
Court Disposition
Application to set aside the freezing injunction refused; freezing injunction continued.
Orders
- Freezing injunction against Mark Cruz continued up to £200,000.
- MM Cruz Developments Ltd added as Second Defendant.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment