Maftoon (t/a Fm Construction Services) v Sayed & Anor
On the balance of probabilities, the contract was between Mr Maftoon and Mr Sayed in his personal capacity, as it was not made clear to Mr Maftoon that Mr Sayed was contracting as agent or director of the company.
- Parties
- Claimant: Farad Maftoon T/A FM Construction Services; First Defendant: Ahmed Sayed; Second Defendant: Lebaneat (Yarm) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 07 July 2020
- Procedural Posture
- Civil / Judgment
- Outcome
- Declaration that the contract was between Mr Maftoon and Mr Sayed personally.
- Legal Topics
- Identity of Contracting Parties, Agency, Construction Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Farad Maftoon T/A FM Construction Services
Claimant
Ahmed Sayed
First Defendant
Lebaneat (Yarm) Limited
Second Defendant
Procedural Posture
Civil / Judgment
Legal Issues
- 1 Whether the contract for building works at 48 High Street, Yarm was entered into by Ahmed Sayed personally or by Lebaneat (Yarm) Limited acting through Ahmed Sayed
Ratio Decidendi
On the balance of probabilities, the contract was between Mr Maftoon and Mr Sayed in his personal capacity, as it was not made clear to Mr Maftoon that Mr Sayed was contracting as agent or director of the company.
Court Disposition
Declaration that the contract was between Mr Maftoon and Mr Sayed personally.
Orders
- Parties invited to agree a form of order to give effect to the judgment.
- If agreement not reached by 12 noon on 13 July 2020, parties to contact court to fix a hearing.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment