Harrison & Ors v Shepherd Homes Ltd & Ors [2011] EWHC 1811 (TCC) (11 July 2011)
SHL's sales contracts impose obligations to carry out design with proper skill and care and to complete works fit for habitation; these obligations are not excluded by entire agreement clauses, do not merge on conveyance, and are protected by statutory controls. Implied terms apply unless expressly and unequivocally excluded, which is not the case here.
- Citation
- [2011] EWHC 1811 (TCC)
- Parties
- Claimants: Mr Andrew Harrison and Others; First Defendant: Shepherd Homes Limited; Second Defendant: National House Building Council; Third Defendant: NHBC Building Control Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 July 2011
- Procedural Posture
- Civil / Trial Judgment
- Outcome
- Liability established against SHL for breach of contract and statutory obligations.
- Legal Topics
- Implied Terms, Entire Agreement Clauses, Defective Premises Act 1972, Unfair Terms in Consumer Contracts Regulations 1999, Unfair Contract Terms Act 1977, Merger Doctrine, Fitness for Habitation, Design and Workmanship Standards
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Mr Andrew Harrison and Others
Claimants
Shepherd Homes Limited
First Defendant
National House Building Council
Second Defendant
NHBC Building Control Services Limited
Third Defendant
Procedural Posture
Civil / Trial Judgment
Legal Issues
- 1 Scope and extent of obligations under sales contracts
- 2 Implied terms regarding design and fitness for habitation
- 3 Effect of entire agreement clause on implied terms
Ratio Decidendi
SHL's sales contracts impose obligations to carry out design with proper skill and care and to complete works fit for habitation; these obligations are not excluded by entire agreement clauses, do not merge on conveyance, and are protected by statutory controls. Implied terms apply unless expressly and unequivocally excluded, which is not the case here.
Court Disposition
Liability established against SHL for breach of contract and statutory obligations.
Orders
- SHL liable to lead Claimants for defective design and construction; damages to be assessed.
- Parties to resolve quantum based on findings; further calculation required.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment