Powell v Lowe [2010] EWCA Civ 1419 (18 October 2010)

Powell v Lowe [2010] EWCA Civ 1419 (18 October 2010)

The agreement between the parties contained implied terms that the renovation and sale of the property would be completed within a reasonable time, and that the defendant would not act to forfeit the lease. The defendant's failure to perform these obligations and the resulting unreasonable delay entitled the claimant to immediate repayment of the loan, notwithstanding the express term linking repayment to sale.

Citation
[2010] EWCA Civ 1419
Parties
Applicant/defendant: Craig Powell; Respondent/claimant: Emma Lowe
Jurisdiction
England and Wales
Judgment Date
18 October 2010
Procedural Posture
Civil Appeal / Appeal From Central London County Court Judgment
Outcome
Appeal dismissed; application refused
Legal Topics
Implied Terms in Contract, Repayment of Loans, Constructive Trusts, Beneficial Interest in Property, Costs Orders

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Craig Powell

Applicant/defendant

Emma Lowe

Respondent/claimant

Procedural Posture

Civil Appeal / Appeal From Central London County Court Judgment

  1. 1 Whether the claimant is entitled to repayment of monies advanced for property purchase as a loan or as a beneficial interest in the property
  2. 2 Whether implied terms should be read into the agreement regarding renovation and sale within a reasonable time
  3. 3 Whether the defendant's failure to renovate and sell within a reasonable time triggers immediate repayment of the loan

Ratio Decidendi

The agreement between the parties contained implied terms that the renovation and sale of the property would be completed within a reasonable time, and that the defendant would not act to forfeit the lease. The defendant's failure to perform these obligations and the resulting unreasonable delay entitled the claimant to immediate repayment of the loan, notwithstanding the express term linking repayment to sale.

Court Disposition

Appeal dismissed; application refused

Orders

  • Defendant to repay £57,662.80 plus £1,744.10 interest to claimant
  • No order as to costs of claim and counterclaim