Pan Ocean Co Ltd v Daelim Corporation [2023] EWHC 391 (Comm) (24 February 2023)

Pan Ocean Co Ltd v Daelim Corporation [2023] EWHC 391 (Comm) (24 February 2023)

The tribunal applied the correct legal test for implication of terms but erred in the content and effect of the implied term. The implied term required both parties to exercise reasonable diligence to arrange reinspection without undue delay, not a strict unilateral obligation on charterers. The vessel was not back...

Source-derived case information.

Citation
[2023] EWHC 391 (Comm)
Parties
Claimant/respondent in Arbitration: Pan Ocean Co Ltd; Defendant/claimant in Arbitration: Daelim Corporation
Jurisdiction
England and Wales
Judgment Date
24 February 2023
Procedural Posture
Appeal From Arbitration Award (section 69 Arbitration Act 1996) / Judgment on Appeal
Outcome
Award remitted to the tribunal for reconsideration in accordance with the judgment.
Legal Topics
Implied Terms in Contracts, Time Charterparties, Off Hire Clauses, Remission of Arbitral Awards
Arbitration Shipping Law Contract Law Implied Terms in Contracts Time Charterparties Off Hire Clauses Remission of Arbitral Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Pan Ocean Co Ltd

Claimant/respondent in Arbitration

Daelim Corporation

Defendant/claimant in Arbitration

Procedural Posture

Appeal From Arbitration Award (section 69 Arbitration Act 1996) / Judgment on Appeal

  1. 1 Whether there was an implied term in the charterparty obliging charterers to have the vessel reinspected without delay after failed holds inspection and notification by the Master
  2. 2 Whether the tribunal applied the correct legal test for implication of terms
  3. 3 Whether the implied term imposed a strict unilateral obligation on charterers

Ratio Decidendi

The tribunal applied the correct legal test for implication of terms but erred in the content and effect of the implied term. The implied term required both parties to exercise reasonable diligence to arrange reinspection without undue delay, not a strict unilateral obligation on charterers. The vessel was not back on hire immediately upon notification of readiness for reinspection; rather, it would be back on hire when reinspection should reasonably have occurred. The matter is remitted to the tribunal to determine compliance with the implied term and financial consequences.

Court Disposition

Award remitted to the tribunal for reconsideration in accordance with the judgment.

Orders

  • The award is remitted to the tribunal to determine what could and should have been done by the parties regarding reinspection, whether either party was in breach, the relevant timescales, and the financial consequences of any breach, including costs.