Balfour Beatty Regional Construction Ltd v Grove Developments Ltd
The contract, as amended by the Tumber schedule, provided for only 23 interim payments up to the contractual date for practical completion. There was no express or implied term entitling BB to further interim payments after valuation 23. The contract satisfied the requirements of sections 109 and 110 of the 1996 Act, so the Scheme did not apply. No separate agreement for further interim payments was reached. Therefore, BB was not entitled to interim payments after valuation 23.
- Parties
- Defendant/appellant: Balfour Beatty Regional Construction Limited; Claimant/respondent: Grove Developments Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 13 October 2016
- Procedural Posture
- Civil Appeal / Appeal From Technology and Construction Court to Court of Appeal
- Outcome
- Appeal dismissed
- Legal Topics
- Interim Payments, Contract Interpretation, Implied Terms, Statutory Scheme for Construction Contracts
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Balfour Beatty Regional Construction Limited
Defendant/appellant
Grove Developments Limited
Claimant/respondent
Procedural Posture
Civil Appeal / Appeal From Technology and Construction Court to Court of Appeal
Legal Issues
- 1 Whether the contract as amended provided for interim payments after valuation 23
- 2 Whether the 1996 Act and the Scheme for Construction Contracts applied to entitle the contractor to further interim payments
- 3 Whether a separate agreement for interim payments after valuation 23 was reached
Ratio Decidendi
The contract, as amended by the Tumber schedule, provided for only 23 interim payments up to the contractual date for practical completion. There was no express or implied term entitling BB to further interim payments after valuation 23. The contract satisfied the requirements of sections 109 and 110 of the 1996 Act, so the Scheme did not apply. No separate agreement for further interim payments was reached. Therefore, BB was not entitled to interim payments after valuation 23.
Court Disposition
Appeal dismissed
Orders
- Declaration that the Defendant has no contractual right to make Interim Application no.24 (or any subsequent application) and has no right to be paid in respect thereof.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment