Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd (No. 2) [2007] EWHC 145 (TCC) (31 January 2007)
The design and fabrication of all roof temporary works (including those undertaken by Hollandia) were excluded from the £12 million lump sum and fell within the cost-plus arrangement under the Supplemental Agreement, as evidenced by the inclusion of 'temp works - roof props' in Schedule 3 Part A and the contemporaneous schedules. Multiplex is not entitled to claim as damages the costs incurred in procuring these works from Hollandia.
- Citation
- [2007] EWHC 145 (TCC)
- Parties
- Claimant/part 20 Defendant: Multiplex Constructions (UK) Limited; First Defendant/part 20 Claimant: Cleveland Bridge UK Limited; Second Defendant: Cleveland Bridge Dorman Long Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 31 January 2007
- Procedural Posture
- Commercial Construction Dispute (preliminary Issue) / Judgment on 11th Preliminary Issue After Trial
- Outcome
- Claim on preliminary issue dismissed; costs of roof temporary works not recoverable as damages by Multiplex.
- Legal Topics
- Interpretation of Construction Contracts, Scope of Subcontractor Obligations, Allocation of Costs for Temporary Works, Damages for Repudiation, Variation and Supplemental Agreements
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Multiplex Constructions (UK) Limited
Claimant/part 20 Defendant
Cleveland Bridge UK Limited
First Defendant/part 20 Claimant
Cleveland Bridge Dorman Long Engineering Limited
Second Defendant
Procedural Posture
Commercial Construction Dispute (preliminary Issue) / Judgment on 11th Preliminary Issue After Trial
Legal Issues
- 1 Whether the design and fabrication of temporary works for the stadium roof fell within the lump sum or cost-plus elements of the Supplemental Agreement post-15 February 2004
- 2 Whether 'temp works - roof props' in Schedule 3 Part A of the Supplemental Agreement included all roof temporary works or only modifications to arch lift turning struts
- 3 Whether Multiplex can claim damages for costs incurred in procuring temporary works from Hollandia
Ratio Decidendi
The design and fabrication of all roof temporary works (including those undertaken by Hollandia) were excluded from the £12 million lump sum and fell within the cost-plus arrangement under the Supplemental Agreement, as evidenced by the inclusion of 'temp works - roof props' in Schedule 3 Part A and the contemporaneous schedules. Multiplex is not entitled to claim as damages the costs incurred in procuring these works from Hollandia.
Court Disposition
Claim on preliminary issue dismissed; costs of roof temporary works not recoverable as damages by Multiplex.
Orders
- It is declared that the design and fabrication of roof temporary works post-15 February 2004 were not within the £12 million lump sum but were subject to cost-plus reimbursement under the Supplemental Agreement.
- Multiplex's claim for damages in respect of costs incurred for roof temporary works is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment