RWE Npower Renewables Ltd v J N Bentley Ltd
Section 2 of the works was not completed until the whole of the penstock pipeline had been completed and tested, as both Option X5 and clause 6.2 should be read together, requiring full completion by the stipulated date.
- Parties
- Claimant/respondent: RWE Npower Renewables Ltd; Defendant/appellant: J N Bentley Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 19 February 2014
- Procedural Posture
- Civil Appeal / Appeal From High Court Judgment
- Outcome
- Appeal dismissed
- Legal Topics
- Interpretation of Contract Terms, Sectional Completion, Liquidated Damages, Order of Precedence in Contract Documents
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
RWE Npower Renewables Ltd
Claimant/respondent
J N Bentley Ltd
Defendant/appellant
Procedural Posture
Civil Appeal / Appeal From High Court Judgment
Legal Issues
- 1 Whether Bentley's obligation for completion of section 2 was governed by clause 6.2 of the Works Information or Option X5 in Part 1 of the Contract Data
- 2 Extent of Bentley's obligation regarding completion and testing of the penstock pipeline
Ratio Decidendi
Section 2 of the works was not completed until the whole of the penstock pipeline had been completed and tested, as both Option X5 and clause 6.2 should be read together, requiring full completion by the stipulated date.
Court Disposition
Appeal dismissed
Orders
- Section 2 of the works not completed until whole penstock pipeline completed and tested
- Bentley's obligation defined by harmonised reading of Option X5 and clause 6.2
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment