CC Construction Ltd v Mincione [2021] EWHC 2502 (TCC) (15 September 2021)
The due date for final payment was not 13 February 2021, as the purported Notice of Completion of Making Good of 13 January 2021 was not valid under clause 2.36 due to absence of defects schedule or instructions under clause 2.35. Therefore, clause 4.12.5.2 did not apply, and the due date was one month from receipt of the Final Statement, i.e., 4 January 2021. The Employer's letter of 18 December 2020 was ineffective to prevent conclusivity of the Final Statement. The adjudicator had jurisdiction to determine conclusivity, and there was no material breach of natural justice regarding liquidated damages set-off. The adjudication decision is enforceable.
- Citation
- [2021] EWHC 2502 (TCC)
- Parties
- Claimant/part 8 Defendant: CC Construction Limited; Defendant/part 8 Claimant: Raffaele Mincione
- Jurisdiction
- England and Wales
- Judgment Date
- 15 September 2021
- Procedural Posture
- Construction Contract Enforcement and Declaratory Relief / Judgment After Remote Hearing on Summary Judgment and Part 8 Claim
- Outcome
- Employer's claim for declaration as to due date dismissed; Contractor's claim for summary judgment granted; adjudication decision enforced.
- Legal Topics
- JCT Design and Build Contract Interpretation, Final Statement Conclusivity, Adjudication Enforcement, Liquidated Damages, Consumer Rights Act 2015
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
CC Construction Limited
Claimant/part 8 Defendant
Raffaele Mincione
Defendant/part 8 Claimant
Procedural Posture
Construction Contract Enforcement and Declaratory Relief / Judgment After Remote Hearing on Summary Judgment and Part 8 Claim
Legal Issues
- 1 What is the correct due date for final payment under the contract?
- 2 Was the Employer's letter effective to prevent the Final Statement becoming conclusive?
- 3 Did the adjudicator have jurisdiction to determine conclusivity?
Ratio Decidendi
The due date for final payment was not 13 February 2021, as the purported Notice of Completion of Making Good of 13 January 2021 was not valid under clause 2.36 due to absence of defects schedule or instructions under clause 2.35. Therefore, clause 4.12.5.2 did not apply, and the due date was one month from receipt of the Final Statement, i.e., 4 January 2021. The Employer's letter of 18 December 2020 was ineffective to prevent conclusivity of the Final Statement. The adjudicator had jurisdiction to determine conclusivity, and there was no material breach of natural justice regarding liquidated damages set-off. The adjudication decision is enforceable.
Court Disposition
Employer's claim for declaration as to due date dismissed; Contractor's claim for summary judgment granted; adjudication decision enforced.
Orders
- No declaration granted as to due date sought by Employer.
- Summary judgment for Contractor for payment of £479,957.80 net of VAT.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment