Coal Action Network, R (on the application of) v Welsh Ministers & Anor

Coal Action Network, R (on the application of) v Welsh Ministers & Anor

Section 26A of the Coal Industry Act 1994 does not apply to authorisations contained in licences granted before its commencement, even if the authorisation was postponed and not yet in force. The Coal Authority's role in determining whether conditions precedent were satisfied did not permit it to revisit the principle of authorising coal mining operations or to consider Welsh policy or climate change impacts. The claim is dismissed on both grounds.

Parties
Claimant: Coal Action Network; First Defendant: Welsh Ministers; Second Defendant: Coal Authority; Interested Party: Energybuild Mining Limited
Jurisdiction
England and Wales
Judgment Date
11 September 2024
Procedural Posture
Judicial Review / Final Judgment
Outcome
Claim dismissed
Legal Topics
Judicial Review, Coal Mining Licensing, Retrospective Legislation, Statutory Powers, Climate Change Policy

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Coal Action Network

Claimant

Welsh Ministers

First Defendant

Coal Authority

Second Defendant

Energybuild Mining Limited

Interested Party

Procedural Posture

Judicial Review / Final Judgment

  1. 1 Whether section 26A of the Coal Industry Act 1994 applies to the deconditionalisation of a pre-existing coal mining licence issued before the section came into force.
  2. 2 Whether the Coal Authority fettered its discretion or failed to take into account material considerations in approving the deconditionalisation application.

Ratio Decidendi

Section 26A of the Coal Industry Act 1994 does not apply to authorisations contained in licences granted before its commencement, even if the authorisation was postponed and not yet in force. The Coal Authority's role in determining whether conditions precedent were satisfied did not permit it to revisit the principle of authorising coal mining operations or to consider Welsh policy or climate change impacts. The claim is dismissed on both grounds.

Court Disposition

Claim dismissed