ERDC Group Ltd. v Brunel University
The court held that the letters of intent prior to 1 September 2002 constituted binding contracts, and work done under them is to be valued under the JCT Valuation Rules. After 1 September 2002, there was no contract, so ERDC is entitled to a quantum meruit, but the valuation is to be primarily by reference to the previously agreed rates and prices, not cost plus, as these were objectively reasonable and used by both parties. Delay/disruption and time-related costs are only allowed where justified, and Brunel's counterclaim for defects/unfinished work abates ERDC's claim only to the extent of the value of benefit conferred, not as damages. The net sum due to ERDC is the assessed value...
- Parties
- Claimant/part 20 Defendant: ERDC Group Limited; Defendant/part 20 Claimant: Brunel University
- Jurisdiction
- England and Wales
- Judgment Date
- 29 March 2006
- Procedural Posture
- Civil (construction Contract Dispute) / Judgment After Full Trial
- Outcome
- Judgment for ERDC Group Limited for the balance of its claim, subject to abatement for defects and sums already paid.
- Legal Topics
- Letters of Intent, Quantum Meruit, Valuation of Construction Works, Delay and Disruption, Counterclaims for Defects
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
ERDC Group Limited
Claimant/part 20 Defendant
Brunel University
Defendant/part 20 Claimant
Procedural Posture
Civil (construction Contract Dispute) / Judgment After Full Trial
Legal Issues
- 1 Whether binding contracts existed prior to 1 September 2002 under letters of intent and their terms
- 2 On what basis the works before and after 1 September 2002 should be valued (contractual/JCT rules or quantum meruit)
- 3 Entitlement to delay/disruption costs and assessment of time-related costs
Ratio Decidendi
The court held that the letters of intent prior to 1 September 2002 constituted binding contracts, and work done under them is to be valued under the JCT Valuation Rules. After 1 September 2002, there was no contract, so ERDC is entitled to a quantum meruit, but the valuation is to be primarily by reference to the previously agreed rates and prices, not cost plus, as these were objectively reasonable and used by both parties. Delay/disruption and time-related costs are only allowed where justified, and Brunel's counterclaim for defects/unfinished work abates ERDC's claim only to the extent of the value of benefit conferred, not as damages. The net sum due to ERDC is the assessed value...
Court Disposition
Judgment for ERDC Group Limited for the balance of its claim, subject to abatement for defects and sums already paid.
Orders
- Brunel University to pay ERDC Group Limited £360,110.09 plus VAT of £63,019.26, total £423,129.35.
- Interest to be awarded in the usual way on sums found due.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment