Vinci Construction UK Limited v Eastwood and Partners (Consulting Engineers) Limited & Anor
Snowden's claim in contract against GHW is statute-barred and must be struck out. Snowden's claim in negligence is not suitable for summary judgment as there is a real prospect of success regarding the limitation issue under section 14A. The contribution claim is sufficiently pleaded and not liable to be struck out at this stage.
- Parties
- Claimant: VINCI CONSTRUCTION UK LIMITED; First Defendant: EASTWOOD AND PARTNERS (CONSULTING ENGINEERS) LIMITED; Second Defendant: SNOWDEN SEAMLESS FLOORS LIMITED; Third Party: GHW CONSULTING ENGINEERS LIMITED
- Jurisdiction
- England and Wales
- Judgment Date
- 11 September 2024
- Procedural Posture
- Civil Technology and Construction / Summary Judgment and Strike Out Applications
- Outcome
- Partial summary judgment and strike out granted; remainder of applications dismissed.
- Legal Topics
- Limitation Period, Negligence, Contribution Claims, Summary Judgment, Strike Out Applications
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
VINCI CONSTRUCTION UK LIMITED
Claimant
EASTWOOD AND PARTNERS (CONSULTING ENGINEERS) LIMITED
First Defendant
SNOWDEN SEAMLESS FLOORS LIMITED
Second Defendant
GHW CONSULTING ENGINEERS LIMITED
Third Party
Procedural Posture
Civil Technology and Construction / Summary Judgment and Strike Out Applications
Legal Issues
- 1 Whether Snowden's claim in negligence against GHW is statute-barred under the Limitation Act 1980
- 2 Whether Snowden's claim for contribution under the Civil Liability (Contribution) Act 1978 discloses a valid cause of action
Ratio Decidendi
Snowden's claim in contract against GHW is statute-barred and must be struck out. Snowden's claim in negligence is not suitable for summary judgment as there is a real prospect of success regarding the limitation issue under section 14A. The contribution claim is sufficiently pleaded and not liable to be struck out at this stage.
Court Disposition
Partial summary judgment and strike out granted; remainder of applications dismissed.
Orders
- Snowden's claim against GHW for breach of contract is struck out as statute-barred.
- GHW's application for summary judgment and/or strike out of the negligence and contribution claims is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment