Henry Boot Construction Ltd. v Alstom Combined Cycles Ltd. [2005] EWCA Civ 814 (16 June 2005)

Henry Boot Construction Ltd. v Alstom Combined Cycles Ltd. [2005] EWCA Civ 814 (16 June 2005)

The right to payment under the contract arises when a certificate is issued or ought to be issued, not when the work is done. Certificates are a condition precedent to payment, but their absence is not a bar to recovery if an arbitrator or court determines a certificate ought to have been issued. Claims for sums...

Source-derived case information.

Citation
[2005] EWCA Civ 814
Parties
Appellant/claimant: Henry Boot Construction Ltd; Respondent/defendant: Alstom Combined Cycles Ltd
Jurisdiction
England and Wales
Judgment Date
16 June 2005
Procedural Posture
Appeal From Arbitration Award / Court of Appeal Judgment
Outcome
Appeal allowed in part; judge arbitrator's conclusion that all or almost all claims were statute-barred overturned for claims included in the final certificate.
Legal Topics
Limitation Periods, Payment Terms, Certification Under Construction Contracts, Statute Barred Claims, Interest on Overdue Payments
Construction Law Contract Law Arbitration Limitation Periods Payment Terms Certification Under Construction Contracts Statute Barred Claims Interest on Overdue Payments

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Henry Boot Construction Ltd

Appellant/claimant

Alstom Combined Cycles Ltd

Respondent/defendant

Procedural Posture

Appeal From Arbitration Award / Court of Appeal Judgment

  1. 1 When does a cause of action arise for interim and final payments under construction contracts?
  2. 2 Are certificates a condition precedent to payment?
  3. 3 Does failure to certify or undervaluation in certificates give rise to new causes of action?

Ratio Decidendi

The right to payment under the contract arises when a certificate is issued or ought to be issued, not when the work is done. Certificates are a condition precedent to payment, but their absence is not a bar to recovery if an arbitrator or court determines a certificate ought to have been issued. Claims for sums omitted from interim certificates are not statute-barred if included in the final certificate, as interim and final certificates give rise to distinct causes of action.

Court Disposition

Appeal allowed in part; judge arbitrator's conclusion that all or almost all claims were statute-barred overturned for claims included in the final certificate.

Orders

  • Claims for sums omitted from interim certificates but included in the final certificate are not statute-barred.
  • Engineer obliged to certify sums in the final certificate regardless of whether they were omitted from interim certificates.