J Sainsbury Plc & Anor v WSP Consulting Engineers Plc & Anor
The amendment to substitute a lower figure for remedial works is refused as it is irrelevant; if the claimants had invoked their rights under the Keller contract, they would not have incurred any loss. The amendment to plead a credit for the cost of the planned extension is permitted, with the consequences to be addressed if and when the claimants seek a consequential amendment. The application to strike out part of the response to further information is refused as unnecessary.
- Parties
- Claimant: J Sainsbury PLC; Claimant: Sainsbury's Supermarkets Limited; Defendant/part 20 Claimant: WSP Consulting Engineers PLC (Formally WSP Kenchington Ford PLC); Part 20 Defendant: Keller Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 04 November 2004
- Procedural Posture
- Civil (construction/engineering Dispute) / Interlocutory Application During Trial (application to Amend Pleadings)
- Outcome
- Application to amend defence regarding remedial works cost refused; application to amend defence regarding extension cost allowed; application to strike out part of response to further information refused.
- Legal Topics
- Mitigation of Loss, Amendment of Pleadings, Damages, Professional Negligence
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
J Sainsbury PLC
Claimant
Sainsbury's Supermarkets Limited
Claimant
WSP Consulting Engineers PLC (Formally WSP Kenchington Ford PLC)
Defendant/part 20 Claimant
Keller Limited
Part 20 Defendant
Procedural Posture
Civil (construction/engineering Dispute) / Interlocutory Application During Trial (application to Amend Pleadings)
Legal Issues
- 1 Whether the defendant should be permitted to amend its defence to substitute a lower figure for remedial works and to plead a credit for the cost of a planned extension.
- 2 Whether the claimants failed to mitigate their loss by not requiring Keller to return to site for further remedial works.
- 3 Whether the claimants should be allowed to amend their response to further information regarding the planned extension.
Ratio Decidendi
The amendment to substitute a lower figure for remedial works is refused as it is irrelevant; if the claimants had invoked their rights under the Keller contract, they would not have incurred any loss. The amendment to plead a credit for the cost of the planned extension is permitted, with the consequences to be addressed if and when the claimants seek a consequential amendment. The application to strike out part of the response to further information is refused as unnecessary.
Court Disposition
Application to amend defence regarding remedial works cost refused; application to amend defence regarding extension cost allowed; application to strike out part of response to further information refused.
Orders
- Defendant's application to amend defence to substitute lower remedial works cost refused.
- Defendant's application to amend defence to plead credit for extension cost allowed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment