Mehjoo v Harben Barker (a firm) & Anor
Claimant entitled to 95% of costs against Second Defendant, assessed on standard basis up to 12 October 2012 and indemnity basis thereafter, with 10% uplift on interest post-Part 36 offer expiry; First Defendant entitled to costs against Claimant; Claimant entitled to indemnity for Grant Thornton disclosure fees; interim payment set at £1.7 million; stay granted subject to security; time for appeal set at 21 days.
- Parties
- Claimant: Hossein Mehjoo; First Defendant: Harben Barker (A Firm); Second Defendant: Harben Barker Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 14 June 2013
- Procedural Posture
- Civil / Post Judgment Costs and Consequential Orders
- Outcome
- Costs and consequential orders issued post-judgment.
- Legal Topics
- Part 36 Offers, Indemnity Costs, Disclosure Orders, Interest on Judgment, Interim Payments, Issue Based Costs Orders
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hossein Mehjoo
Claimant
Harben Barker (A Firm)
First Defendant
Harben Barker Limited
Second Defendant
Procedural Posture
Civil / Post Judgment Costs and Consequential Orders
Legal Issues
- 1 Entitlement to costs for First Defendant
- 2 Basis for costs assessment against Second Defendant (standard or indemnity)
- 3 Deduction/set-off from Claimant's costs
Ratio Decidendi
Claimant entitled to 95% of costs against Second Defendant, assessed on standard basis up to 12 October 2012 and indemnity basis thereafter, with 10% uplift on interest post-Part 36 offer expiry; First Defendant entitled to costs against Claimant; Claimant entitled to indemnity for Grant Thornton disclosure fees; interim payment set at £1.7 million; stay granted subject to security; time for appeal set at 21 days.
Court Disposition
Costs and consequential orders issued post-judgment.
Orders
- First Defendant awarded costs against Claimant, to be assessed if not agreed.
- Second Defendant to pay 95% of Claimant's costs on standard basis up to 12 October 2012 and indemnity basis thereafter, with 10% interest uplift post-Part 36 offer expiry.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment