Alstom Signalling Ltd. (t/a Alstom Transport Information Solutions) v Jarvis Facilities Ltd [2004] EWHC 1285 (TCC) (28 May 2004)
Alstom's questions and queries regarding Application 32 were not sufficiently specific and focused to justify withholding payment under Clause 2.4 of Schedule F. The contract did not provide an effective final date for payment, so the statutory Scheme applied, requiring payment within 17 days of due date. Alstom failed to serve a valid withholding notice and was in breach of contract and statute. Jarvis was entitled to payment as applied for, subject to agreed amendments.
- Citation
- [2004] EWHC 1285 (TCC)
- Parties
- Claimant/defendant: Alstom Signalling Limited (trading as Alstom Transport Information Solutions); Defendant/claimant: Jarvis Facilities Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 28 May 2004
- Procedural Posture
- Construction Contract Dispute / Post Adjudication, High Court Judgment
- Outcome
- Judgment for Jarvis Facilities Limited
- Legal Topics
- Payment Provisions, Adjudication, Withholding Notices, Final Account, Pain/gain Share, Housing Grants, Construction and Regeneration Act 1996
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Alstom Signalling Limited (trading as Alstom Transport Information Solutions)
Claimant/defendant
Jarvis Facilities Limited
Defendant/claimant
Procedural Posture
Construction Contract Dispute / Post Adjudication, High Court Judgment
Legal Issues
- 1 Whether Alstom was entitled to withhold payment from Jarvis under Application 32
- 2 Whether Alstom's questions and queries were sufficiently specific under the contract
- 3 Whether Alstom complied with statutory requirements for withholding notices
Ratio Decidendi
Alstom's questions and queries regarding Application 32 were not sufficiently specific and focused to justify withholding payment under Clause 2.4 of Schedule F. The contract did not provide an effective final date for payment, so the statutory Scheme applied, requiring payment within 17 days of due date. Alstom failed to serve a valid withholding notice and was in breach of contract and statute. Jarvis was entitled to payment as applied for, subject to agreed amendments.
Court Disposition
Judgment for Jarvis Facilities Limited
Orders
- Alstom to pay Jarvis £1,328,250 plus interest as determined
- Payment to be made within statutory timeframe
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment