Yuanda (UK) Company Ltd v Multiplex Construction Europe Ltd & Anor [2020] EWHC 468 (TCC) (28 February 2020)
The Guarantee is a performance bond, not an on-demand bond. Multiplex is not entitled to make a valid demand under the Guarantee unless damages are established and ascertained under the contract, taking into account all sums due or to become due to Yuanda. The demand made on 17 January 2020 was premature, as the ascertainment process had not concluded. The Guarantee expires on 4 April 2020. Yuanda is not entitled to continuation of the injunction; the interim injunction is discharged.
- Citation
- [2020] EWHC 468 (TCC)
- Parties
- Applicant/claimant: Yuanda (UK) Company Limited; First Respondent/defendant: Multiplex Construction Europe Limited; Second Respondent/defendant: Australia and New Zealand Banking Group Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 28 February 2020
- Procedural Posture
- Injunction Proceedings (technology and Construction Court) / Judgment on Continuation/discharge of Interim Injunction
- Outcome
- Interim injunction discharged; Yuanda not entitled to continuation.
- Legal Topics
- Performance Bonds, Guarantees, Injunctions, Contract Interpretation, Adjudication, Fraud Allegations
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Yuanda (UK) Company Limited
Applicant/claimant
Multiplex Construction Europe Limited
First Respondent/defendant
Australia and New Zealand Banking Group Limited
Second Respondent/defendant
Procedural Posture
Injunction Proceedings (technology and Construction Court) / Judgment on Continuation/discharge of Interim Injunction
Legal Issues
- 1 Type of instrument: performance bond or on-demand bond
- 2 Requirements for valid call under the Guarantee
- 3 Entitlement to interim and continued injunction
Ratio Decidendi
The Guarantee is a performance bond, not an on-demand bond. Multiplex is not entitled to make a valid demand under the Guarantee unless damages are established and ascertained under the contract, taking into account all sums due or to become due to Yuanda. The demand made on 17 January 2020 was premature, as the ascertainment process had not concluded. The Guarantee expires on 4 April 2020. Yuanda is not entitled to continuation of the injunction; the interim injunction is discharged.
Court Disposition
Interim injunction discharged; Yuanda not entitled to continuation.
Orders
- Interim injunction restraining payment under the Guarantee is discharged.
- Bank and Multiplex may proceed in accordance with the Guarantee's terms.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment