O'Rourke Construction Ltd v Healthcare Support (Newcastle) Ltd & Ors [2014] EWHC 2595 (TCC) (28 July 2014)
The Independent Tester is to consider only the Completion Criteria in Schedule 12, Part 2, when deciding whether to issue a Phase Certificate of Practical Completion. Minor breaches or nonconformities that do not materially affect the amenity or functional use of the building do not prevent certification. Disputes between Project Co and the Trust are irrelevant to the Independent Tester's judgment. The Trust retains remedies for defects post-completion.
- Citation
- [2014] EWHC 2595 (TCC)
- Parties
- Claimant: Laing O'Rourke Construction Ltd (formerly Laing O'Rourke Northern Ltd); 1st Defendant: Healthcare Support (Newcastle) Ltd; 2nd Defendant: Newcastle upon Tyne Hospitals NHS Foundation Trust
- Jurisdiction
- England and Wales
- Judgment Date
- 28 July 2014
- Procedural Posture
- Part 8 Claim (cpr) / Judgment on Application for Declaratory Relief
- Outcome
- Application granted in part; declaration made as to the role of the Independent Tester; other declarations refused.
- Legal Topics
- Practical Completion, Certification, Private Finance Initiative (pfi), Declaratory Relief, Independent Tester Role
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Laing O'Rourke Construction Ltd (formerly Laing O'Rourke Northern Ltd)
Claimant
Healthcare Support (Newcastle) Ltd
1st Defendant
Newcastle upon Tyne Hospitals NHS Foundation Trust
2nd Defendant
Procedural Posture
Part 8 Claim (cpr) / Judgment on Application for Declaratory Relief
Legal Issues
- 1 Whether the Independent Tester must withhold the Phase Certificate of Practical Completion for any breach of contract or only for failure to meet Completion Criteria
- 2 Interpretation of Completion Criteria under Construction Contract and Project Agreement
- 3 Effect of disputes between Project Co and Trust on certification
Ratio Decidendi
The Independent Tester is to consider only the Completion Criteria in Schedule 12, Part 2, when deciding whether to issue a Phase Certificate of Practical Completion. Minor breaches or nonconformities that do not materially affect the amenity or functional use of the building do not prevent certification. Disputes between Project Co and the Trust are irrelevant to the Independent Tester's judgment. The Trust retains remedies for defects post-completion.
Court Disposition
Application granted in part; declaration made as to the role of the Independent Tester; other declarations refused.
Orders
- Declaration that the Independent Tester should consider completion against the Completion Criteria in Schedule 12, Part 2, without influence from disputes between Project Co and the Trust.
- Refusal of declarations relating to third party certifiers, hypothetical situations, and matters of fact and degree.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment