Olympic Delivery Authority v Persons Unknown [2012] EWHC 1012 (Ch) (04 April 2012)
The ODA, as exclusive licensee, is entitled to relief for private nuisance caused by protesters' obstruction of access to the site. The protesters' conduct is unlawful and not protected by Articles 10 and 11 ECHR to the extent it obstructs the ODA's rights. The interim injunction is necessary and proportionate to restrain unlawful activity, with the balance of risk of injustice favouring the ODA, but only for a short period to allow affected parties to seek advice and respond.
- Citation
- [2012] EWHC 1012 (Ch)
- Parties
- Claimant: Olympic Delivery Authority; Defendants: Persons Unknown; Interested Party: Ms. K. Andrews; Interested Party: Mr. M. Doyle
- Jurisdiction
- England and Wales
- Judgment Date
- 04 April 2012
- Procedural Posture
- Interim Injunction Application / First Instance, Interim Relief
- Outcome
- Interim injunction granted until 18 April 2012
- Legal Topics
- Private Nuisance, Public Nuisance, Interim Injunctions, Human Rights Balancing, Protest Law, Exclusive Licence, Freedom of Expression, Freedom of Assembly
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Olympic Delivery Authority
Claimant
Persons Unknown
Defendants
Ms. K. Andrews
Interested Party
Mr. M. Doyle
Interested Party
Procedural Posture
Interim Injunction Application / First Instance, Interim Relief
Legal Issues
- 1 Whether the conduct of protesters constitutes private and/or public nuisance actionable by the ODA
- 2 Whether the ODA as exclusive licensee has standing to claim in nuisance
- 3 Whether an interim injunction restraining protester activities is necessary and proportionate given the engagement of Articles 10 and 11 ECHR
Ratio Decidendi
The ODA, as exclusive licensee, is entitled to relief for private nuisance caused by protesters' obstruction of access to the site. The protesters' conduct is unlawful and not protected by Articles 10 and 11 ECHR to the extent it obstructs the ODA's rights. The interim injunction is necessary and proportionate to restrain unlawful activity, with the balance of risk of injustice favouring the ODA, but only for a short period to allow affected parties to seek advice and respond.
Court Disposition
Interim injunction granted until 18 April 2012
Orders
- Defendants restrained from obstructing access to the ODA site and related activities as per revised draft order until 18 April 2012
- Matter to return to court on 18 April 2012 for reconsideration of continuation of injunction
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment