MTU was not obliged to continue performance of the Engine Sub-Contract after valid termination for Gamit's repudiatory breach. The purchase orders did not create independent contractual obligations. Title to the disputed parts did not pass to Gamit because the parts were not replaced and thus were not 'surplus' or 'replaced' within the meaning of the contract. No conversion occurred. Any loss claimed by Gamit was too remote to be recoverable from MTU.

Citation
[2011] EWHC 989 (Comm)
Parties
Claimant: Gamit Limited; First Defendant: Saudi Arabian Airlines Corporation; Second Defendant: MTU Maintenance Hannover GmbH
Jurisdiction
England and Wales
Judgment Date
18 April 2011
Procedural Posture
Commercial Claim / High Court Trial Judgment
Outcome
Claim dismissed
Legal Topics
Repudiatory Breach, Title to Goods, Conversion, Remoteness of Damages, Interpretation of Contractual Terms

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 2 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Gamit Limited

Claimant

Saudi Arabian Airlines Corporation

First Defendant

MTU Maintenance Hannover GmbH

Second Defendant

Procedural Posture

Commercial Claim / High Court Trial Judgment

  1. 1 Whether MTU was obliged to replace disputed engine parts with new parts after termination of the Engine Sub-Contract
  2. 2 Whether Gamit acquired title to disputed parts under the Engine Agreement or subsequent court order
  3. 3 Whether MTU's actions constituted conversion

Ratio Decidendi

MTU was not obliged to continue performance of the Engine Sub-Contract after valid termination for Gamit's repudiatory breach. The purchase orders did not create independent contractual obligations. Title to the disputed parts did not pass to Gamit because the parts were not replaced and thus were not 'surplus' or 'replaced' within the meaning of the contract. No conversion occurred. Any loss claimed by Gamit was too remote to be recoverable from MTU.

Court Disposition

Claim dismissed