Van Der Giessen-De-Noord Shipbuiilding Division BV v Imtech Marine & Offshore BV
The tribunal committed serious irregularity by failing to address the waiver/estoppel defence, the agreed variation procedure, and by double-counting sums for additional works, and by awarding interest at 10% without giving the parties an opportunity to address the appropriateness of that rate. These failures caused substantial injustice to GN. The appropriate remedy is to set aside the affected parts of the award and require reconsideration by the tribunal with an umpire present.
- Parties
- Claimant/respondent in Arbitration: Van der Giessen-de-Noord Shipbuilding Division B.V.; Defendant/claimant in Arbitration: Imtech Marine & Offshore B.V.
- Jurisdiction
- England and Wales
- Judgment Date
- 26 November 2008
- Procedural Posture
- Arbitration Challenge (section 68 Arbitration Act 1996) / Judgment on Application to Set Aside/remit Arbitral Award
- Outcome
- Award set aside in part and remitted for reconsideration with an umpire; directions for further submissions/orders reserved.
- Legal Topics
- Serious Irregularity (section 68 Arbitration Act 1996), Waiver/estoppel, Variation Procedure in Contracts, Interest Awards, Double Recovery/double Counting, Scope of Work Disputes
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Van der Giessen-de-Noord Shipbuilding Division B.V.
Claimant/respondent in Arbitration
Imtech Marine & Offshore B.V.
Defendant/claimant in Arbitration
Procedural Posture
Arbitration Challenge (section 68 Arbitration Act 1996) / Judgment on Application to Set Aside/remit Arbitral Award
Legal Issues
- 1 Whether the arbitral tribunal committed serious irregularity under section 68 of the Arbitration Act 1996 by failing to address essential issues and defences
- 2 Whether the tribunal failed to deal with the waiver/estoppel defence
- 3 Whether the tribunal failed to address the agreed variation procedure and its impact
Ratio Decidendi
The tribunal committed serious irregularity by failing to address the waiver/estoppel defence, the agreed variation procedure, and by double-counting sums for additional works, and by awarding interest at 10% without giving the parties an opportunity to address the appropriateness of that rate. These failures caused substantial injustice to GN. The appropriate remedy is to set aside the affected parts of the award and require reconsideration by the tribunal with an umpire present.
Court Disposition
Award set aside in part and remitted for reconsideration with an umpire; directions for further submissions/orders reserved.
Orders
- Paragraphs 21–23 (HVAC Variation Claim No 1), including the award of €1,347,960, set aside
- Paragraphs 55–59 (Additional Work/Increased Scope of Work), including the award of €1,000,000, set aside
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment