Multiplex Constructions (UK) Ltd v Cleveland Bridge UK Ltd [2006] EWHC 1341 (TCC) (05 June 2006)
The court held that the Supplemental Agreement was a full and final settlement of all claims and disputes existing before 15 February 2004, except as expressly reserved. Multiplex was not entitled to revalue the agreed gross valuation as at 15 February 2004 or make deductions except as permitted by the contract. The conduct of Multiplex in issuing certificates 37 and 38 and withholding payment constituted repudiatory breach. CB was entitled to treat the contract as repudiated and claim damages. The contractual cap on liability applied except where claims fell outside its scope.
- Citation
- [2006] EWHC 1341 (TCC)
- Parties
- Claimant/part 20 Defendant: Multiplex Constructions (UK) Limited; First Defendant/part 20 Claimant: Cleveland Bridge UK Limited; Second Defendant: Cleveland Bridge Dorman Long Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 05 June 2006
- Procedural Posture
- Consolidated Civil Action (technology and Construction Court) / Trial of Preliminary Issues
- Outcome
- Judgment for the defendants (CB and Cleveland Bridge Dorman Long Engineering Limited) on the preliminary issues; Multiplex found to have repudiated the contract.
- Legal Topics
- Subcontract Disputes, Breach of Contract, Repudiation, Damages, Valuation of Works, Settlement Agreements, Adjudication, Variation and Omission of Works
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Multiplex Constructions (UK) Limited
Claimant/part 20 Defendant
Cleveland Bridge UK Limited
First Defendant/part 20 Claimant
Cleveland Bridge Dorman Long Engineering Limited
Second Defendant
Procedural Posture
Consolidated Civil Action (technology and Construction Court) / Trial of Preliminary Issues
Legal Issues
- 1 Whether the Heads of Agreement and Supplemental Agreement resolved all prior claims and disputes between the parties
- 2 Whether Multiplex was entitled to revalue works and make deductions in certificates 37 and 38
- 3 Whether CB or Multiplex repudiated the contract
Ratio Decidendi
The court held that the Supplemental Agreement was a full and final settlement of all claims and disputes existing before 15 February 2004, except as expressly reserved. Multiplex was not entitled to revalue the agreed gross valuation as at 15 February 2004 or make deductions except as permitted by the contract. The conduct of Multiplex in issuing certificates 37 and 38 and withholding payment constituted repudiatory breach. CB was entitled to treat the contract as repudiated and claim damages. The contractual cap on liability applied except where claims fell outside its scope.
Court Disposition
Judgment for the defendants (CB and Cleveland Bridge Dorman Long Engineering Limited) on the preliminary issues; Multiplex found to have repudiated the contract.
Orders
- Multiplex not entitled to revalue or deduct from the agreed gross valuation as at 15 February 2004 except as contractually permitted.
- CB entitled to damages for repudiatory breach, subject to contractual cap.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment