Tele2 International Card Company SA & Ors v Post Office Ltd [2008] EWHC 158 (QB) (25 February 2008)
The Post Office was entitled to terminate the Agreement under clause 11.4.1 for breach of clause 3.10.2, as the breach was incapable of remedy and clause 16 precluded waiver or affirmation by delay, neglect, or forbearance. There was no novation or assignment to C3 (UK); only Tele2 Ireland, as party to the Agreement, was entitled to claim damages, subject to proof of loss. The Post Office's continued performance did not amount to affirmation overriding its contractual right to terminate.
- Citation
- [2008] EWHC 158
- Parties
- Claimant: Tele2 International Card Company SA; Claimant: Kub 2 Technology Limited (formerly C3 Calling Card Company (Ireland) Limited); Claimant: Kub 7 Technology Limited (formerly Calling Card Company (UK) Limited); Defendant/part 20 Claimant: Post Office Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 25 February 2008
- Procedural Posture
- Commercial Contract Dispute / High Court Judgment
- Outcome
- Claim dismissed
- Legal Topics
- Termination of Contract, Novation, Assignment, Breach of Contract, Damages, Waiver, Affirmation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Tele2 International Card Company SA
Claimant
Kub 2 Technology Limited (formerly C3 Calling Card Company (Ireland) Limited)
Claimant
Kub 7 Technology Limited (formerly Calling Card Company (UK) Limited)
Claimant
Post Office Limited
Defendant/part 20 Claimant
Procedural Posture
Commercial Contract Dispute / High Court Judgment
Legal Issues
- 1 Whether the Post Office validly terminated the Agreement for breach of clause 3.10.2
- 2 Whether Tele2 Ireland or C3 (UK) was entitled to claim damages
- 3 Whether the Post Office affirmed the Agreement by continued performance
Ratio Decidendi
The Post Office was entitled to terminate the Agreement under clause 11.4.1 for breach of clause 3.10.2, as the breach was incapable of remedy and clause 16 precluded waiver or affirmation by delay, neglect, or forbearance. There was no novation or assignment to C3 (UK); only Tele2 Ireland, as party to the Agreement, was entitled to claim damages, subject to proof of loss. The Post Office's continued performance did not amount to affirmation overriding its contractual right to terminate.
Court Disposition
Claim dismissed
Orders
- Claimants' claims for damages for wrongful termination and breach dismissed
- Post Office's cross-claims for expiry revenue and additional fees addressed according to contractual entitlement
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment